Speeding up the progress of the 500kV line 3 project

Tuesday, March 12, 2024 | 18:46:43

172 views

On the afternoon of March 12, Comrade Nguyen Hong Dien, Member of the Party Central Committee, Minister of Industry and Trade chaired an online conference on accelerating the progress of the 500kV line 3 project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen). Attending the conference at Thai Binh bridge were Comrade Nguyen Quang Hung, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee and leaders of relevant departments, branches, units and localities.

Comrade Nguyen Quang Hung, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee spoke at the Thai Binh province bridge.

According to the report, the 500kV line 3 project from Quang Trach to Pho Noi has completed signing contracts for 225/226 packages; site clearance work has handed over 1,177/1,177 column foundation locations and 160/503 anchor spaces, while 343 anchor spaces have not yet been handed over; construction work has been carried out simultaneously on the entire route at 1,174 locations, and foundation casting has been completed at 184 locations. Mobilizing machinery, equipment, workers from 33 companies and 334 teams...

Delegates attend the online conference.

At the conference, representatives of relevant sectors and localities reported a summary of the progress of the implementation of the 500 kV line 3 project, including: site clearance, handover of column foundation locations, line corridors, etc.

Speaking at the Thai Binh bridge, the Standing Vice Chairman of the Provincial People's Committee reported to the Minister of Industry and Trade that Thai Binh province has handed over 107 column foundation locations in 4 districts: Vu Thu, Dong Hung, Hung Ha, Quynh Phu to the investor and the construction contractor. At present, the contractor has completed the foundation of 17 locations, is constructing 88 locations, 3 locations are erecting columns and the route corridor has handed over 36 anchorages. In the coming time, Thai Binh province will continue to direct departments, branches, localities, and units to closely coordinate with the construction contractor to proactively source construction materials to speed up the project's construction progress. Proactively resolve the fastest work related to the project according to assigned functions and tasks to complete the project and put it into operation according to the striving goals.

Concluding the conference, the Minister of Industry and Trade acknowledged and highly appreciated the drastic participation of the localities in their efforts to hand over 100% of the foundation pits to the contractors. With the goal of striving to complete the project before June 30 this year and ensuring quality, the Minister requested that the sectors and localities review a number of tasks related to the project to promptly resolve any problems during implementation. The provinces where the project passes through should strongly urge and direct the departments, sectors and localities to coordinate with the investor to continue to do a good job of propaganda and mobilization of affected households to create consensus to complete the site clearance for the anchorage and route corridor, creating favorable conditions for the construction units to speed up the progress. Require contractors to closely coordinate with local authorities and related units to mobilize maximum human and material resources, promote a sense of responsibility, be proactive, creative, and apply modern scientific and technological solutions to implement the project. For Vietnam Electricity Group and the National Power Transmission Corporation, it is necessary to determine the role of the project investor to properly fulfill their responsibilities and urge contractors to speed up construction progress to ensure quality. Do a good job of inspection, supervision, and urging contractors to concentrate all resources at construction sites according to the project commitment time.

Manh Thang


Source

Comment (0)

No data
No data

Same tag

Same category

Luc Yen, a hidden green gem
Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product