Photo: Vietnam+
Online conference at 9 points of connection in the provinces where the project passes through. At the Hai Duong point, there were representatives of departments, branches and localities related to the project attending.
Concluding the conference, comrade Nguyen Hong Dien, Minister of Industry and Trade, requested localities and units to strive to complete the handover of anchorage areas to construction contractors before May 15. Localities continue to urge and direct departments, branches, districts and towns where the project passes through to strengthen propaganda and mobilize households to soon agree and hand over the remaining anchorage areas so that investors can implement construction on schedule. The work of clearing the power line corridor is completed according to plan to ensure safety before operation...
According to Mr. Nguyen Anh Tuan, General Director of Vietnam Electricity Group (EVN), by early May, a total of 4 projects had handed over 100% of the column foundation locations and 377/503 (about 75%) of the anchor spaces, while 126/503 anchor spaces had not been handed over, of which 2 provinces had completed the handover of the anchor spaces, namely Quang Binh and Ninh Binh .
In Hai Duong, as of May 6, only 2 more households in Thanh Mien and Binh Giang districts belonging to 2 areas have received support for site clearance. Gia Loc district has signed and approved compensation plans for 3 households. Currently, there are still land clearance issues in 2 districts Binh Giang (1 household) and Ninh Giang (3 households) belonging to 2 areas.
Regarding construction progress, as of May 6, in Hai Duong, 67 foundation positions have been completed, an increase of 9 foundations; 33 positions have been erected, an increase of 6 columns compared to April 23...
THANH HOASource