Part 2: "Overcoming the sun and rain" to bring the project to the finish line

Việt NamViệt Nam21/06/2024


Regardless of the weather, whether it is sunny or rainy, windy or hot, the construction site of the 500kV line 3 in Thai Binh province is always bustling with a competitive working atmosphere. All construction forces share the same determination to overcome the sun and rain to bring the project to the finish line on schedule.

Electricity workers and officials "brave the sun and rain", determined to bring the project to the finish line on schedule.

Work 3 shifts, 4 shifts

The national key project 500kV line 3 is currently entering the final stage with the target date of June 30, 2024, the project must be completed and energized in phase 1 according to the direction of the Prime Minister. These days, leaders, commanders and workers at all levels at the construction site are highly focused on constructing the final items of the project. Despite the scorching June sun, with temperatures sometimes approaching 400C, workers and laborers still stick to the project, regardless of difficulties and hardships, maintaining 3 shifts and 4 shifts.

Human resources and modern machinery were mobilized to focus on constructing the 500 kV line 3 in Thai Binh.

At the location of column 129 in Tu Tan commune (Vu Thu), dozens of electricians of Thai Binh Power Company coordinated with the construction unit to brave the scorching heat to transport, assemble steel components and erect the column. Despite the hard work, everyone was happy and always reminded each other to "eat quickly, sleep quickly", "one person does the work of two" to strive to soon complete the column construction and installation to prepare for pulling the wire.

Mr. Hoang Ngoc Dieu, a worker at Thai Binh Power Company, said: Joining the shock team to support the construction of the 500kV line 3, we clearly understand the importance of the project, so we feel very honored to be able to construct this important line. With enthusiasm, responsibility and love for the job, we will devote ourselves to achieving the highest productivity and quality. The workers are also very excited because during the construction process, we always receive timely attention and encouragement from the provincial leaders, the Northern Power Corporation and the leaders of Vu Thu district.

At the construction site of column 207 in Quynh Khe commune (Quynh Phu), there is always a force of 17-30 people working in 3 shifts; the workers also work day and night, making efforts to complete the assigned tasks.

Mr. Ma Ngoc Khanh, a worker at Bac Kan Electricity Company, shared: As electricity workers, we are tasked with strengthening the 500kV line 3 project passing through Thai Binh province. The weather has been very harsh these past few days, sometimes scorching hot, sometimes pouring rain, but we still try to stay at the construction site, find every solution to overcome the situation, and are determined to complete the pole erection stage to prepare for pulling the wire according to the assigned schedule.

Continuing the glorious tradition of the electricity industry

It can be said that the spirit of daring to think, daring to do, daring to take responsibility, the spirit of creative labor competition and the determination to overcome the sun and rain during the construction of the 500kV North-South transmission line, circuit 1, years ago is being vividly recreated at all construction sites of the 500kV transmission line, circuit 3 project.

Despite the hard work, workers at the 500 kV line 3 construction site in Thai Binh are still excited and happy to work.

Mr. Do Duc Thien, General Director of the Northern Power Corporation, said: Despite the difficult conditions of constructing the 500kV line 3, engineers and workers of the power sector units have made every effort, not afraid of hardships, and determined to complete the assigned tasks.

Working groups regularly inspect and grasp the situation at the construction site and promptly find solutions to remove difficulties and obstacles, speed up construction progress, and ensure absolute safety for workers. With courage, intelligence, and enthusiasm for the electricity flow from the Central region to the North, the team of cadres, engineers, electricity workers and forces participating in the 500kV line 3 Quang Trach - Pho Noi project will continue to write the epic of the renovation period on this historic project.

(continued)

Khac Duan - Manh Thang



Source: https://baothaibinh.com.vn/tin-tuc/4/202015/ky-2-vuot-nang-thang-mua-dua-cong-trinh-ve-dich

Comment (0)

No data
No data

Same tag

Same category

Luc Yen, a hidden green gem
Spreading national cultural values ​​through musical works
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product