On the afternoon of December 13, Mr. Nguyen Duc Tho - Vice Chairman of Hai Phong City People's Committee inspected the site clearance work and the construction status of the project to invest in building the road connecting the coastal road (Km1+00) to Van Bun intersection (Coastal road connecting road project) in Do Son district, Hai Phong city.
Mr. Nguyen Duc Tho (in white hat) - Vice Chairman of Hai Phong City People's Committee inspected the progress and site clearance of the traffic project in Do Son district.
After inspecting the field and listening to reports from departments, branches, Do Son district, investors and contractors of the project, Mr. Nguyen Duc Tho requested the People's Committee of Do Son district to focus on site clearance work, handing over the site to the construction unit no later than December 31, 2023. At the same time, prepare plans and organize enforcement before the Lunar New Year of Giap Thin 2024.
Mr. Nguyen Duc Tho also assigned the People's Committee of Do Son District to coordinate with the contractor and the supervisory unit to re-establish the progress plan, clearly defining the responsibilities of the locality and related units if the project's progress is delayed. For the cleared land, the People's Committee of Do Son District and the wards in the area will strictly manage the land area on both sides of the road, not allowing people to illegally encroach, causing difficulties for management after the project is completed and put into use.
Site clearance work for the trillion-dollar traffic project in Do Son district, Hai Phong city has not yet been completed.
Previously, Nguoi Dua Tin published an article "Hai Phong: Removing difficulties in site clearance for a trillion-dollar traffic project in Do Son" with the content: In order to effectively exploit the coastal road project connecting Hai Phong - Thai Binh to help promote local socio-economic development, on May 1, 2021, the People's Committee of Do Son District, Hai Phong City started the project to invest in building a road connecting from the coastal road (Km1+00) to Van Bun intersection (Coastal road connecting road project) in the area.
The project has a total length of 6.2km, passing through 3 wards of Do Son district, including: Minh Duc, Ngoc Xuyen and Van Huong. The initial total investment of the project is nearly 833 billion VND, invested by the People's Committee of Do Son district. The project implementation period is from 2019 to 2023. After adjustment, the total investment increased to more than 959 billion VND, the project implementation period lasts until the end of 2024.
The contractor arranges construction workers in areas where the site has been handed over.
According to information from the People's Committee of Do Son District, Hai Phong City, to serve the project, the locality proceeded to reclaim 16.76 hectares of land from 324 households and 6 organizations in 3 wards: Ngoc Xuyen, Minh Duc and Van Huong (all in Do Son District, Hai Phong City).
Because the recovered land area does not have residential land and does not require resettlement, by the end of 2021, Ngoc Xuyen Ward, Do Son District, Hai Phong City has completed the site clearance work and handed over the entire clean site to the construction unit. However, in Van Huong Ward and Minh Duc Ward, the site clearance work encountered many difficulties .