Vietnam.vn - Nền tảng quảng bá Việt Nam

Huong Son Hydropower Plant to operate in the fourth quarter of 2024

Việt NamViệt Nam07/09/2024


Huong Son Hydropower Plant investment project has a total installed capacity of 39.4 MW, connected to the national grid at the 2x25MVA-110/35/22KV Linh Cam - Ha Tinh transformer station.

Ha Tinh Economic Zone Management Board issued Decision No. 186/QD-KKT on approving the adjustment of investment policy of Huong Son Hydropower Plant project.

Previously, the Project was approved for adjustment by this Board in Decision No. 01/QD-KKT dated January 2, 2024.

Nhà máy thuỷ điện Hương Sơn
Huong Son Hydropower Plant.

Accordingly, the implementation progress content is adjusted as follows: "Implementation progress - phase 2 - Huong Son 2 Hydropower Plant starts implementation from the first quarter of 2021 and is completed and put into use in the fourth quarter of 2024".

The Ha Tinh Economic Zone Management Board assigned Huong Son Hydropower Joint Stock Company the responsibility to focus all resources on construction, completing and putting the project into operation according to the approved schedule and project objectives.

Land use area is 189,107 ha. Project implementation period is 50 years from August 25, 2008 (date of first investment certificate issuance).

The Huong Son Hydropower Plant investment project has a total installed capacity of 39.4 MW, connected to the national grid at the 2x25MVA-110/35/22KV Linh Cam - Ha Tinh transformer station, divided into 2 phases.

Phase 1, the plant has a capacity of 33 MW (Huong Son 1 Hydropower Plant), including 2 units of shell turbines, each unit of 16.5 MW. Phase 2 has a capacity of 6.4 MW (Huong Son 2 Hydropower Plant), including 2 units of 3.2 MW each. The project's objective is to invest in construction, manage and operate the hydropower plant and produce and trade electricity.

The total investment capital of the project is more than 1,103,766 billion VND, of which phase 1 has a total capital of more than 812,444 billion VND (equity capital of more than 231,539 billion VND and loan capital of more than 580,904 billion VND; phase 2 has a total investment capital of more than 291,322 billion VND (equity capital of 91,322 billion VND, loan capital of 200 billion VND.

Regarding the implementation progress, phase 1 started in 2005 and was completed and put into use in 2012; phase 2 started in the first quarter of 2021 and was completed and put into use in the fourth quarter of 2024. The project implementation location is in Son Kim 1 commune, Huong Son district, Ha Tinh province (in the Cau Treo International Border Gate Economic Zone).

Source: https://baodautu.vn/ha-tinh-nha-may-thuy-dien-huong-son-van-hanh-trong-quy-iv2024-d224021.html


Comment (0)

No data
No data

Same tag

Same category

36 military and police units practice for April 30th parade
Vietnam not only..., but also...!
Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product