In the bustling atmosphere of the last days of the year, on key projects of Ha Tinh city, construction units are rushing to complete items so that the city can welcome the new year 2024 bright - green - clean - beautiful.
For many days, Phan Dinh Phung Street seemed to have not slept. From early morning until late at night, construction units mobilized maximum means and workers to complete construction items, bury power lines, dismantle and clean up wires to ensure the central street has space and neat landscape before the moment of welcoming the new year.
Ha Tinh City Electricity and VNPT Ha Tinh units coordinated to handle overhead power lines and optical cables to replace them with modern underground cable systems.
In recent days, although there have been times when the weather in Ha Tinh City has been very cold and the temperature has dropped, it has not affected the working spirit of workers at the construction site.
Workers complete the sidewalk paving, creating a bright, airy and modern space for the street.
Along with Phan Dinh Phung Street, the Nguyen Cong Tru Street upgrade project is also at its peak of progress.
Determined to complete before Tet, Vinh Phu Construction Company Limited has implemented a "rolling" construction solution, assembling and connecting drainage components, building technical trench infrastructure and paving sidewalks. According to Mr. Pham Van Duc, a technical officer of Vinh Phu Construction Company Limited, in order for people to celebrate the New Year, the company has maintained the construction progress to complete the items according to the motto "do it as it is done, clean it up"; on the other hand, it has cleaned up construction materials so as not to affect the joyful atmosphere of the New Year.
At the construction site of the extended Xuan Dieu road project (from the Northern urban beltway to Ngo Quyen street), the sounds of machines and people are bustling.
The 1.8 km long project will start construction in September 2023 with a total investment of VND 234 billion. According to the construction units, to ensure the progress and volume of construction, the construction site often has dozens of types of machinery, construction vehicles and hundreds of workers working hard.
At this point, the project has completed 40% of the volume. Units are focusing on the construction of foundation, ditch, precast concrete and relocation of power line infrastructure.
The closer to the end of the year, the more urgent and rushed the working atmosphere is to ensure the capital disbursement plan is as planned.
Mr. Nguyen Cao Thang - technical officer of Khanh Mon Construction Company Limited said that the unit has taken full advantage of time and favorable weather to speed up construction progress. On days with good weather and no rain, the unit organizes overtime work at night. Despite the large volume of pressure, the spirit of the whole company is highly focused, ensuring the city's capital disbursement plan. Up to this point, the company has completed 100% of the disbursement plan for 2023.
2023 marks an important milestone when the Eastern Ring Road Project of Ha Tinh City officially starts construction. After 10 months of construction (from February 2023), the strategic road to expand the city's space has now taken shape.
To date, the project has completed over 30% of the construction volume, meeting the capital disbursement plan.
In the last days of the year, the construction atmosphere is always bustling and urgent.
According to construction units, in the coming days, the construction site of the Eastern Ring Road Project of Ha Tinh City will work "through" the holidays to create a new atmosphere, a new beginning with many favorable and smooth conditions in the new year 2024.
According to the City's Land Fund Development and Investment Project Management Board, in general, the projects being implemented in the area meet the construction schedule, making an important contribution to the disbursement of local capital. As of December 28, 2023, the total disbursed capital from the central, provincial and municipal budgets of the Ha Tinh City Land Fund Investment and Development Project Management Board is VND 936,985 million, estimated at 90% of the assigned capital plan. The unit is continuing to closely monitor the progress of works and projects, urging and creating all conditions for contractors to deploy effective and safe construction solutions, ensuring the quality of works. |
Nguyen Oanh - Dinh Nhat