The disbursement rate of public investment capital in the first quarter was low because transitional projects are focusing on completing the volume to pay for advance capital and extended capital; new projects are carrying out the work of preparing construction drawings - estimates, preparing to select contractors... The investment preparation work of some projects expected to start construction is still slow, so it is not yet eligible to be added to the public investment plan for 2025.
The Provincial People's Committee said that some projects are stuck with construction sites or land procedures (agreements to set compensation prices, land acquisition procedures). In addition, component project 4: Compensation, support, resettlement of Ho Chi Minh City - Moc Bai expressway section through Tay Ninh province was assigned a large capital plan (equivalent to 25% of the 2025 plan) but implementation is slow due to dependence on the progress of investment project approval by Ho Chi Minh City.
In order to complete the public investment plan in 2025, including promoting the disbursement of public investment capital to reach 50% by June 30, 2025, the Provincial People's Committee requested the heads of departments, branches, and Chairmen of People's Committees of districts, towns, and cities to resolutely and focus on accelerating the progress of compensation and site clearance to implement key projects; promptly handle the difficulties and obstacles of investors related to the land valuation process, compensation plans, etc.
Complete compensation and site clearance for component project 4 - Ho Chi Minh City - Moc Bai Expressway (phase 1) before April 30, 2025 to start the project on schedule and projects at Ba Den Mountain National Tourist Area.
Continue to adjust and supplement the medium-term public investment plan for the period 2021-2025 and 2025 from projects that are unlikely to fully disburse the allocated capital to new projects that have completed investment procedures according to regulations and projects that need additional capital to speed up project implementation progress; overcome the subjective, inactive situation, and concentrate disbursement in the last months of the year, ensuring the completion of the assigned public investment plan targets.
The Department of Agriculture and Environment advises the Provincial People's Committee on solutions to speed up the progress of compensation and site clearance; closely coordinates with relevant units to promptly handle problems and difficulties of investors related to land valuation procedures and compensation plans; proactively supports and guides the Department of Natural Resources and Environment and the District Land Fund Development Center in the process of implementing procedures related to compensation and site clearance.
The Department of Finance urges investors to promptly implement the project, report to the Provincial People's Committee any problems (if any) and propose solutions to ensure the completion of the target "By June 30, 2025, reach 50%, by September 30, 2025, reach 75% and by the end of the 2025 plan, reach 100% of the assigned public investment plan".
Investors must coordinate to review and strictly control the capacity of contractors during the process of organizing contractor selection and negotiating and signing contracts, ensuring a sufficient number of commanders, technicians, and appropriate workers to execute the packages, and not allowing the situation of not being able to arrange enough human resources to perform according to the required plan, affecting the project progress.
At the same time, urge contractors to drastically speed up construction progress in the first months of the year; compare actual disbursement results and commitments every month to take timely corrective and remedial measures; strengthen supervision and inspection of construction quality, regularly organize on-site inspections, and resolutely handle violations in the implementation of construction contracts.
In addition, the investor urgently completes the settlement documents and finalizes the completed projects, coordinates with the construction unit to fully and promptly carry out the procedures to disburse capital according to the construction progress and the assigned capital plan; promptly prepares the progress plan, coordinates with relevant units to implement the compensation and site clearance plan in parallel with the process of preparing the project documents and technical economic reports immediately after the decision on capital allocation to prepare for project investment; promptly handles problems and difficulties in the land valuation process, compensation plan, etc.
Nhi Tran
Source: https://baotayninh.vn/den-30-6-2025-ty-le-giai-ngan-von-dau-tu-cong-phai-dat-50--a188040.html
Comment (0)