Accordingly, 9 provinces and cities achieved a disbursement rate of public investment capital to implement the National Target Program of over 60%, and 6 provinces achieved less than 30%.
Specifically, 9 provinces and cities achieved a disbursement rate of public investment capital to implement the National Target Program of over 60% or more, including: Hau Giang (87.6%), Vinh Long (74.3%), Ninh Thuan (74.2%), Tien Giang (65.7%), Bac Lieu (65%), Lam Dong (64.9%), Thanh Hoa (64.5%), Yen Bai (63.2%), Tra Vinh (61%).
6 provinces have disbursement rates below 30%: Binh Phuoc (6.5%), Ha Tinh (13.8%), Ca Mau (18.1%), Hoa Binh (24.6%), Phu Yen (25.3%), Thai Binh (26.9%); in which Binh Phuoc has not allocated capital for the National Target Program on Sustainable Poverty Reduction.
The Ministry of Finance said that the disbursement of public investment capital to implement national target programs has improved significantly. By the end of August 2024, the disbursement rate of this capital source reached 43.5%, equivalent to about VND 11,838 billion absorbed.
However, there are still some ministries, provinces and cities that are slow in implementation such as the Ethnic Committee, the Ministry of Culture, Sports and Tourism, the Vietnam Cooperative Alliance; Phu Tho, Bac Giang, Lai Chau, Thai Binh, Quang Nam, Binh Thuan, Dak Lak, Dak Nong...
According to the Ministry of Finance, the reason why all capital has not been allocated is because the projects are being implemented and approved, so they are not eligible for capital allocation.
To speed up the disbursement progress, the Ministry of Finance recommends that the Prime Minister direct ministries, central agencies and localities to request program/project/sub-project/component owners and People's Committees to promptly grasp difficulties and obstacles in local implementation to guide, promulgate or submit to competent authorities to promulgate policy mechanisms to create a legal corridor for localities to organize implementation.
For ministries, central and local agencies that have not yet fully allocated the central budget capital plan for 2024, it is necessary to urgently complete procedures and allocate capital; in case capital has been allocated, it is requested to send it to the Ministry of Finance for synthesis.
At the same time, the Ministry of Finance requested localities to review and allocate capital for National Target Programs in accordance with the objectives, subjects, locations and support content, ensuring implementation in accordance with regulations.
Source: https://baohaiduong.vn/con-nhieu-tinh-thanh-cham-giai-ngan-von-dau-tu-cong-chuong-trinh-muc-tieu-quoc-gia-396109.html