Proactively construct before the rainy season
On the afternoon of July 16, Deputy Minister of Transport Le Anh Tuan directly inspected the entire project site of component 1, Khanh Hoa - Buon Ma Thuot expressway.
After listening to the investor's report and recommendations, the Deputy Minister acknowledged the efforts of the investor and contractor in implementing the project, and the coordination and support of the locality (Ninh Hoa Town, Khanh Hoa). Up to now, the project's progress has had positive changes.
Deputy Minister Le Anh Tuan requested that investors and contractors, after receiving the site, need to speed up construction.
Deputy Minister Le Anh Tuan requested the investor, the Khanh Hoa Province Traffic Construction Investment Project Management Board, to closely coordinate with the locality, focus on removing obstacles, speed up site clearance and resettlement to ensure that people who give up land for the project will soon have new housing.
The investor needs to coordinate with the government and relevant units to complete the land clearance work to relocate the 220kV, 110kV, and 35kV power lines. From there, relocate the high-voltage and medium-voltage power lines in July, creating favorable conditions for the contractor to ensure the project's progress.
Mr. Pham Van Hoa, Deputy Director of the Khanh Hoa Province Traffic Construction Investment Project Management Board, reported on the project implementation status to the Deputy Minister.
"Contractors must mobilize human resources and equipment to construct local sections that have been handed over. Investors and contractors must have daily and weekly construction plans, especially when the rainy season is coming," said the Deputy Minister.
Deputy Minister Le Anh Tuan also requested investors to pay more attention to the source of construction materials for the project. Contractors must comply with environmental sanitation regulations and ensure traffic safety during the transportation of construction materials.
Construction site of Khanh Hoa - Buon Ma Thuot expressway.
"The Khanh Hoa - Buon Ma Thuot Expressway connects the Central Highlands region with neighboring areas, connecting the two provinces of Khanh Hoa and Dak Lak. Therefore, the section through Ninh Hoa Town (Khanh Hoa) needs to connect traffic with industrial parks, seaports, and local tourist areas," the Deputy Minister emphasized.
Construction efforts in difficult terrain
At component project 1 of the Khanh Hoa - Buon Ma Thuot expressway project, Reporting to Deputy Minister Le Anh Tuan, Mr. Pham Van Hoa - Deputy Director of the Project Management Board of Traffic Construction Investment of Khanh Hoa province said that by mid-July, Ninh Hoa town had achieved 74% site clearance.
The construction site for contractors is nearly 18km long (over 60%). At the 2.8km long natural forest section, the investor has converted the purpose of using the forest that is currently harvesting forest products.
Contractor for construction of Van Phong - Nha Trang expressway overpass project.
On the route, there are 6 220kV, 110kV, medium and low voltage power systems; 69 water, telecommunication and lighting systems. Many of these technical infrastructure systems are being approved by the Project Management Board for design and contractor selection for construction in July.
To make way for the project, Ninh Hoa Town has arranged for people to relocate to the Ha Thanh resettlement area (Ninh Giang Ward). Up to now, the construction progress of this resettlement area has reached 85%. The entire project is expected to be completed in July this year.
According to Mr. Hoa, taking advantage of the sunny weather and terrain, in the XL01 and XL02 packages, contractors are mobilizing nearly 160 pieces of equipment, 550 engineers and technical workers to speed up the construction of roadbeds, drainage culverts, overpasses, beam casting, site clearance, and construction of service roads...
Despite the land acquisition problem, capital disbursement has so far reached about 20%.
Construction on many sections of the Khanh Hoa - Buon Ma Thuot highway is still going on despite site clearance problems.
Mr. Pham Van Hoa also said: "Based on the construction progress and actual situation of the construction site, it is expected that by the end of 2025, component project 1 will be completed and put into operation the section from Km0 - Km 8+500.
From there, it is possible to put into independent operation the connecting section from Van Phong - Nha Trang expressway to the beginning of the route intersecting with National Highway 1 to follow National Highway 26B to move down to Van Phong port area to transport goods.
Component 1 of the Khanh Hoa - Buon Ma Thuot Expressway project through Khanh Hoa is 32km long, with a design speed of 100km/h. The starting point is at Km 0+00, the intersection between National Highway 26B and National Highway 1 (in the Nam Van Phong port area, Ninh Hoa town). The end point is at Km 32+00 (in Ninh Tay commune, Ninh Hoa town).
The project has a total investment of more than 5,600 billion VND. Implementation period is from 2022 - 2027.