Carrying out the task of compensation, support, site clearance and resettlement of the Khanh Hoa - Buon Ma Thuot Expressway Project (referred to as the Project), up to now, the People's Committee of Krong Pac district has approved the compensation and support plan with a total area of 221.79 ha/223.11 ha, corresponding to the route length of 33.295 km/33.314 km (reaching 99.94%).
The Compensation, Support and Resettlement Council of the Khanh Hoa - Buon Ma Thuot Expressway Project in Krong Pac district has handed over the site to the Provincial Traffic Construction Investment and Agriculture and Rural Development Project Management Board (the project investor) with a total area of 219.11 hectares corresponding to a route length of about 32.15 km.
Construction of Khanh Hoa - Buon Ma Thuot Expressway Project through Ea Knuec Commune. |
The Land Fund Development Center of Krong Pac district has received and paid compensation and support costs of more than 546 billion VND.
The People's Committee of Krong Pac district has also coordinated with units to review and propose adjustments to the planning of 3 types of forests with a total area of 61.51 hectares of production forest land located in 5 communes: Ea Kenh, Ea Yong, Hoa Tien, Ea Uy, Vu Bon (of which 34.73 hectares are highways and 34.78 hectares are mines).
Of the 14 households eligible for resettlement, the District People's Committee has allocated land with land use fees to 2 households in Ea Knuec commune. The remaining households will continue to be considered for resettlement according to regulations in the Northeast area of Phuoc An town, Ea Kenh residential area and Ea Knuec residential area.