On the afternoon of April 19, Comrade Luu Van Ban, Member of the Standing Committee of the Provincial Party Committee, Permanent Vice Chairman of the People's Committee of Hai Duong province chaired a meeting of the Council for Appraisal of Public Investment Projects managed by the province and listened to reports from relevant departments, branches and units on resolving difficulties in the fields of transportation, natural resources and environment, and public investment in the province.
Regarding the difficulties and problems in determining the investment costs for construction of residential areas, urban areas and residential areas in the province, Comrade Luu Van Ban, Standing Vice Chairman of the Provincial People's Committee, proposed that for projects with an area of 20 hectares or more, the construction investment capital rate announced annually by the Ministry of Construction can be applied to determine the construction investment costs.
For projects with an area of less than 20 hectares, the district-level People's Committee shall hire a consulting unit to establish a project design as the basis for reporting the total project investment estimate; the district-level People's Committee shall consult the Department of Construction and the Department of Planning and Investment for comments so that localities can ensure standards and regulations as a basis for determining the total project investment capital, then invite bids.
For projects of more than 20 hectares without special works, the capital pressure for investment in construction of technical infrastructure works shall comply with the regulations of the Ministry of Construction or apply the plan assigned to the District People's Committee to hire a consulting unit to establish a basic design and estimate the total investment of the project. both are ok
Regarding the investment content of the project to renovate and upgrade National Highway 37 from National Highway 18 to An Linh intersection (Chi Linh), Mr. Luu Van Ban, Standing Vice Chairman of the Provincial People's Committee, emphasized that the Provincial People's Committee will chair a working session with the Government Office, the Ministries of Transport, Planning and Investment, Finance, Natural Resources and Environment on the project to unify related issues such as scale and investment capital. The Ministry of Transport is requested to study the investment in the road surface from km87+403-km92+900 in accordance with the approved planning, consider shortening the project implementation time; speed up the project investment progress...
The project to renovate and upgrade National Highway 37 through Con Son - Kiep Bac was approved by the Ministry of Transport in 2011, however, due to funding difficulties, it has not been able to be implemented.
Implementing the conclusion of Prime Minister Pham Minh Chinh at the working session with the leaders of Hai Duong province (March 2024), the Ministry of Transport has deployed the preparation of a report proposing the investment policy to renovate and upgrade National Highway 37 through Con Son - Kiep Bac with a length of 12.3 km, of which the km87 + 403 - km92 + 900 section has a scale of 4 lanes; the km92 + 900 - km99 + 680 section has a scale of 2 lanes. The total investment of the project is nearly 2,300 billion VND. The investment capital is from the state budget (medium-term public investment capital for the period 2021 - 2025, the period 2025 - 2030; additional capital, savings or surplus of the public investment plan, other legal capital sources). Implementation period is from 2023-2025.
Commenting on this project, the Ministry of Planning and Investment requested the Ministry of Transport to coordinate with Hai Duong province to agree on the investment scale, investment method, and specifically propose the expected investment capital for the project...
Regarding the implementation of the project to renovate and upgrade provincial road 395 (section from km16+750 - km23+920) and the road leading from Cay bridge to provincial road 394, Standing Vice Chairman of the Provincial People's Committee Luu Van Ban agreed with the proposal of the Binh Giang District People's Committee. Comrade Luu Van Ban requested specialized departments and branches to guide and support the District People's Committee in moving technical infrastructure works in accordance with current procedures and regulations, and continue to coordinate with the District People's Committee to promptly resolve difficulties and problems arising during the construction process...
According to the report of Binh Giang District People's Committee, the current progress of the entire project has only reached 18%. Regarding site clearance, the entire project involves 724 plots of land of households, equivalent to a length of 7.97 km. Up to now, the investor has handed over 50% of the total project area. Of which, the site has been cleared and handed over to the contractor for construction of the entire area related to agricultural land and traffic corridor land of households, equivalent to about 3.7 km...
Currently, the project is facing difficulties due to the scarcity of materials; the geological layer of some locations where the embankment is built is weaker than the design documents. The relocation of technical infrastructure works including 6 pumping stations, 6.7 km of low-voltage power lines, 0.59 km of 35 kV power lines and 2 transformer stations in Long Xuyen, Tan Viet and Vinh Hong communes is facing difficulties...
Regarding the construction of the Hai Duong Provincial Political School at a new location, the Standing Vice Chairman of the Provincial People's Committee requested relevant units to adjust the size of the auditorium to 300 seats, but it can be mobilized to 350 seats for special events; reduce the size of the dormitory area to 20 rooms. For the functional rooms according to the requirements for building a national standard political school, it is still implemented, meeting the minimum requirements of the regulations, but must be based on the actual needs of the school...
According to the report, the construction scale of the Provincial Political School at the new location includes the following items: the principal's office; a hall with a capacity of 350 people; a classroom building with 5 lecture halls, 8 classrooms... The total area is 3.08 hectares, the total project investment is more than 278 billion VND.
At this meeting, the Provincial People's Committee also gave its opinion on the proposal of Dai Son One Member Co., Ltd. (Hai Duong City) to donate all assets of illegal construction works on the land area of the Traditional Medicine Hospital.
Standing Vice Chairman of the Provincial People's Committee Luu Van Ban affirmed that the province will accept this project to avoid waste and loss of money of the state, investors and people, and at the same time assign the Department of Finance to carry out procedures to receive the assets. The Department of Finance is responsible for coordinating with the Department of Health and the People's Committee of Hai Duong City, based on the needs and wishes of the Traditional Medicine Hospital, to propose a reuse plan to serve the hospital's specialized activities and people's health care. The hospital needs to plan to use the assets for specific purposes, if necessary, supplement the land use planning in accordance with the hospital's planning...