Tien Giang has issued 12 licenses for river sand exploitation. |
Following the direction of the Prime Minister, Tien Giang province supplied 15.95 million m3 of sand for filling 5 key transport projects in the Southern region. By March 21, 2025, the province had allocated 17 mines for 5 projects, with a total reserve of more than 13.556 million m3 .
Up to now, the province has issued 12 river sand mining licenses. The total volume granted is more than 9.698 million m3 ; 5 mines are in the process of licensing, with a total volume of over 3.858 million m3 . It is expected that these mines will be licensed in April 2025; the remaining 2.393 million m3 will be allocated to My Luong mine, Thoi Son mine will be transferred according to a special mechanism after recovery and a part of the remaining reserves of 2 special mining areas (Construction Joint Stock Company 368 and Truong Son Construction Corporation).
Of which, the Ring Road 3 Project, Ho Chi Minh City, has a target of 6.6 million m3 , according to the plan to assign 7 mines. Up to now, 5 mining licenses have been granted for 5 mining areas including: Hoa Hung 5, Vam Cai Thia, Hoa Khanh 1, Hoa Hung 6, Nam Con Da. By March 21, 2025, enterprises have exploited and supplied the project with over 26,000 m3 .
For the Chau Doc - Can Tho - Soc Trang Expressway Project, the target is 4.55 million m3 . According to the plan to assign 5 mines, up to now, 3 mining licenses have been granted at 3 mines including: Hoa Hung 4, Ngu Hiep 1, An Nhon. Enterprises have approved plans to ensure traffic safety, set up buoys, prohibit shore markers; prepare documents to lease water surface land; fulfill financial obligations. It is expected to be exploited before March 31, 2025.
For the Can Tho - Ca Mau Expressway Project, the target is 2 million m3 . According to the plan to assign 1 mine, 1 Mining License has been granted at Binh Duc mine, with a reserve of 592,300 m3 . The enterprise has approved the plan to ensure traffic safety, set up buoys, prohibit shore markers; prepare documents to lease water surface land; fulfill financial obligations. It is expected to be exploited before March 31, 2025.
For the Ho Chi Minh Road Project, the Rach Soi - Ben Nhat and Go Quao - Vinh Thuan sections, the target is 1.8 million m3 . According to the plan to assign 1 mine, 1 Mining License has been granted at Hoa Hung 1 mine, with a total reserve of over 1.823 million m3 to supply the project. Enterprises have approved plans to ensure traffic safety, set up buoys, prohibit shore markers; prepare documents for leasing water surface land; fulfill financial obligations. It is expected to be exploited before March 31, 2025.
For Component Project 2 of the Cao Lanh - An Huu Expressway Construction Project, Phase 1, the assigned target is 950,000 m3 . Up to now, the province has assigned 2 mines (exploitation areas according to special mechanisms) to Construction Joint Stock Company 368 and Truong Son Construction Corporation. The total volume assigned according to project requirements is 1.266 million m3 . By March 21, 2025, the 2 mines have exploited and supplied the project with over 71,800 m3 .
ANH THU