Ending 2024 with excellent results in completing production and business tasks, Khe Cham Coal Company - TKV plans to produce 2 million tons of coal in 2025, marking The company's highest production milestone ever.
In 2024, Khe Cham Coal Company was assigned to produce 1.8 million tons of coal, consume 1.8 million tons, dig 14,300m of tunnel, cut 4,750m of tunnel... With the attention and direction of the Group's leaders, especially the initiative and efforts of the staff, the Company has overcome difficulties, especially the damage caused by storm No. 3 to exceed the production and business plan targets for 2024.
Accordingly, coal production reached 1.840 million tons, equal to 102.2% of the yearly plan (an increase of 40,000 tons compared to the plan); in which, mechanized coal output reached the highest ever with an output of 286,762 tons, equal to 220.6%, coal consumption was 1.802 million tons, the tunnel length reached 14,620m, the tunnel length reached 5,450m. Average salary reached 21.4 million VND/person/month.
In particular, in recent times, the Company has continued to focus on mechanization in mining and tunneling to increase labor productivity, improve production efficiency, as well as mechanize the transportation of equipment, materials, travel, improve working conditions, reduce labor for workers, etc. Notably, the RJKY-55/25/1500 cable car system for carrying people at the upper pit 14.2 at levels -100 to -300 will be put into use from August 2024. This system helps improve the travel conditions of workers, increase working time for units at Mining Site 2 and Tunneling Site 3, thereby improving labor productivity, speeding up the progress of mining and tunneling to prepare for production, creating an exploitation area for the longwalls in the Southwest area of Seam 14.2 in the period of 2024-2030 according to the production and business plan approved by the Group.
Based on the achieved production and business results, by 2025, Khe Cham Coal aims to produce 2 million tons of coal, dig 15,000m of tunnels, consume 2 million tons, and earn an average salary of more than 20 million VND/person/month. Mr. Le Dinh Duong, Party Secretary and Director of Khe Cham Coal Company, said: Since the fourth quarter of 2024, the unit has proactively prepared for increased output in the 2025-2030 period and the following years; developed a technical plan for deep mining of Khe Cham III mine and submitted it to the Group for approval. Along with that, Furnace 14.2-2 of Exploitation Site 6 is a light-weight synchronous mechanized furnace with a capacity of 250,000 tons/year, which has also been put into operation by the Company since December 16, 2024.
With the output increasing to 2 million tons, marking the highest output of Khe Cham Coal ever, the requirement for preparing production areas has also increased. This requires specialized departments to promote the creativity of employees, advise on solutions to promote the capacity of synchronous mechanized longwalls; have plans to dig tunnels to prepare and reserve production areas and equipment to meet production needs, review and update technical and technological indicators to ensure they are suitable for production reality. Focus on propaganda work, labor safety training, building safety habits for employees, direct managers such as foremen and deputy foremen need to participate closely in safety training...
Mr. Hoang Chan Phu, a worker at the 2nd Mining Site, Khe Cham Coal Company, shared: After the New Year holiday, we returned to work with the excitement of the first days of the new year, determined to compete in production right from the first days of the year, while ensuring the highest safety for people and equipment, machinery, and assets of the unit. This year, we workers celebrated the Lunar New Year very happily thanks to the thoughtful care of the Company's leaders and unions.
Immediately after the Lunar New Year holiday, Khe Cham Coal Company will launch emulation movements to encourage employees to make efforts in each shift, take advantage of favorable weather, successfully complete production and business plans for each month, each quarter and the whole year of 2025, and make achievements to celebrate the 40th anniversary of the Company's founding on January 1 (1986-2026).