On the morning of March 19, at the 32nd session, the People's Council of Quang Ngai province voted to approve a draft resolution on stopping the investment project to build 4 routes: Phan Boi Chau extension, Ton Duc Thang extension, An Duong Vuong extension and the route located between the Conference Center, the square and the land on Hai Ba Trung street axis.
Previously, in 2017, this project was approved by the Chairman of the Quang Ngai Provincial People's Committee with a total investment of 150 billion VND, sourced from the provincial budget, and implemented from 2018-2020. Up to now, the next steps have not been organized.
Currently, the location of the investment project to build the above 4 routes, the People's Committee of Quang Ngai City has approved the detailed planning of Thach Bich Green Park in Decision No. 918/QD-UBND dated March 13, 2023 and locally adjusted in Decision No. 958/QD-UBND dated March 25, 2024 (in this planning, there is no longer a route located between the Conference Center, the square and the land on the Hai Ba Trung street axis).
Meanwhile, according to the provisions of the 2024 Law on Public Investment, the condition for deciding on investment policies for programs and projects is: "not overlapping with programs and projects that have had investment policy decisions or investment decisions".
In order to have a basis for implementing the Thach Bich Green Park project, the investment project to build the above 4 roads has been decided by the Provincial People's Council to stop the investment policy.
In addition, at the 32nd session, the People's Council of Quang Ngai province also passed resolutions related to the Thach Bich Green Park project such as investment portfolio, capital allocation, etc.
From there, in order to "remove" legal obstacles to quickly implement the Thach Bich Green Park investment project, eliminating the nearly 3-decade-long suspended planning situation in the dyke zone II (residential group 6, Le Hong Phong ward, Quang Ngai city).
“Recently, the people of residential group 6 have been frustrated because the project has been slow to implement. Today, the People's Council has approved everything related to the Thach Bich Green Park project such as the investment portfolio, capital allocation... ensuring full legality, so that when the Provincial People's Committee directs, the Quang Ngai City People's Committee has a basis to proactively implement it" - Secretary of the Provincial Party Committee, Chairwoman of the Quang Ngai Provincial People's Council Bui Thi Quynh Van affirmed.
The Thach Bich Green Park project will be implemented in the 2024-2027 period, with a total investment of nearly VND900 billion and an area of about 8.1 hectares. The project is expected to help people escape the impact of "suspended" planning that has lasted for nearly 30 years.
Source: https://kinhtedothi.vn/quang-ngai-go-vuong-phap-ly-de-lam-cong-vien-cay-xanh-thach-bich.html