On the afternoon of February 24, a working delegation of the province led by Mr. Hoang Van Thach, member of the Provincial Party Committee, Vice Chairman of the Provincial People's Committee inspected the progress of site clearance and relocation of power line infrastructure for the Dong Dang (Lang Son) - Tra Linh (Cao Bang) Expressway Construction Investment Project in Thach An district. Accompanying the delegation were leaders of a number of departments, branches and Dong Dang - Tra Linh Expressway Joint Stock Company.
Currently, for the compensation and site clearance work of the Dong Dang (Lang Son) - Tra Linh (Cao Bang) Expressway Construction Investment Project, the district has approved the plan and estimate for compensation to support the relocation of graves, and paid for trees and crops for 100% of households; completed the resettlement plan for 66 cases eligible for dispersed resettlement; organized a resettlement lottery for 39 households eligible for resettlement (phase 1), of which 29 households are part of the project.
Regarding the relocation of the 110KV power line in Tuc Nga hamlet, Duc Xuan commune, the district has organized a propaganda meeting with 17 households located within the area of land clearance. Up to now, the architectural assets of households whose land has been recovered have been measured and counted, and a provisional compensation budget of 222.9 million VND has been established, and 14/17 households have been paid.
For the current boundary expansion locations, the district has received land clearance measurement files from 3 communes: Le Lai, Duc Xuan, Dong Khe town, with a route length of 9.34 km, an area of about 18.86 ha. The district has propagated and cleared the land in Duc Xuan commune and is conducting measurement and counting. For Thuy Hung commune, the Land Clearance Council has coordinated with the project enterprise to count trees on the land for households to facilitate construction implementation.
Currently, compensation payment still has some difficulties and problems. Land compensation plan, compensation cost estimate, resettlement support for residential land have not been approved; some architectural property categories are not included in the compensation price, so the process of pricing architectural property is facing many difficulties. Some cases of registration for centralized resettlement do not meet the conditions.
Concluding the meeting, Vice Chairman of the Provincial People's Committee Hoang Van Thach requested: Thach An district urgently reviews and counts all cases of concentrated resettlement households, has a plan for people to move and hand over the site to the construction unit in the first week of March. Coordinate with the project enterprise to develop a timely support plan for scattered resettlement households. Closely follow the grassroots, strengthen propaganda, mobilize households to temporarily relocate to other locations to hand over the site to the construction unit, and soon complete the site clearance work.
Agreeing with the district's proposals and recommendations, Vice Chairman of the Provincial People's Committee Hoang Van Thach requested the district to continue to coordinate with the Department of Natural Resources and Environment to review and supplement the land price list to submit to the Provincial People's Committee. The Provincial Traffic Construction Investment Project Management Board coordinates to relocate the electrical infrastructure, to be completed before March 31, 2025. At the same time, coordinate with the project enterprise, the district and related departments and branches to report to the Provincial People's Committee, promptly remove difficulties and obstacles. Determined and determined to strive to open the entire route by December 31, 2025 as planned.
After the working session, the working delegation inspected the site at the proposed location for dispersed resettlement to clear the ground for bridge construction at km 62 +500, Le Lai commune; the site clearance point for the residential culvert area at km 55 +068, Tuc Nga hamlet, Duc Xuan commune.
Hoai An