TPO - By the end of the first quarter of 2024, the disbursement rate of public investment capital for key projects and works in Dong Nai province only reached more than 6.3% of the plan.
On April 8, information from the Department of Planning and Investment of Dong Nai province said that as of March 13, the total disbursed capital for key projects and works in Dong Nai was more than 313 billion VND, reaching 6.33% of the capital plan allocated by the Provincial People's Committee.
Dong Nai riverside road project is being implemented |
Accordingly, the disbursement rate of public investment capital for key projects and works of the province in the first 3 months of 2024 is still low. Dong Nai Department of Planning and Investment said that the main reason is that the units have not yet implemented the compensation and site clearance of the project. At the same time, in January 2024, the units focused on disbursing the public investment capital plan for 2023, so in the first months of 2024, there was not much volume to pay and had to repay the advance payment in 2023.
To speed up the progress of key projects and works, and the progress of public investment disbursement, the Department of Planning and Investment of Dong Nai requested that the units assigned to carry out construction work and site clearance compensation work urgently coordinate with departments and branches to handle difficulties and problems according to the direction of the Dong Nai Provincial People's Committee. In particular, the Provincial People's Committee requested the units to focus on implementing the work, speeding up right from the beginning of the year to soon complete key projects and works.
Along with that, the People's Committee of Dong Nai province has just issued a directive on accelerating the implementation of key projects and works in the province. Accordingly, the disbursement of public investment capital for key projects and works in the province in 2024 is one of the top important political tasks of all levels and sectors and is a criterion to assess the level of task completion of heads of agencies and units.
In 2024, the Provincial People's Committee aims to strive for the disbursement rate of public investment capital for key projects and works in the province to reach over 95% of the capital plan assigned by the Provincial People's Committee.
In 2024, the total public investment capital directly assigned by the Dong Nai Provincial People's Committee to the planning targets for projects under the provincial management is more than 9.1 trillion VND. Of which, the total capital allocated for key projects and works of the province is more than 4.9 trillion VND (more than 438 billion VND higher than in 2023), accounting for nearly 54% of the detailed capital allocated for the province's projects.
Source
Comment (0)