'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early

Báo Tiền PhongBáo Tiền Phong15/03/2024


TPO - ACV and a consortium of contractors are urgently constructing the runway of Long Thanh airport, completing the project 3 months ahead of schedule.

After more than 6 months of starting construction of package 4.6 - construction and installation of equipment for the runway, taxiway, and apron of Long Thanh International Airport, the runway has now taken shape.

Vietnam Airports Corporation (ACV) and the consortium of contractors are speeding up progress and are determined to complete the project before April 30, 2025, 3 months ahead of schedule.

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 1

Long Thanh airport's runway is 4,000m long and 70m wide and can accommodate the most advanced aircraft today.

ACV has directed the joint venture contractor to mobilize more than 350 machines and equipment along with nearly 1,500 engineers and workers to make the most of the weather and vigorously carry out the construction.

Up to now, the construction of the runway is following the schedule, basically completing the ground and sand foundation items; the crushed stone layer is over 70% completed.

Images of officers, engineers and workers constructing the runway of Long Thanh airport.

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 2

Workers are assembling formwork to prepare for pouring concrete on the runway.

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 3

Hot weather is favorable for concrete construction work, the temperature at the construction site at peak times increases above 40oC

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 4

The runway is being poured the first layer of concrete.

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 5
'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 6
'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 7

Hot weather, concrete surface must be covered with water sacks to keep moist

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 8
According to the runway design, in addition to compacting the roadbed, this is the first concrete layer 38cm thick, the runway will be poured with a second concrete layer 40cm thick.
'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 9

The runway is being compacted in preparation for pouring concrete.

'Teaming up in the sun' to bring Long Thanh airport runway to the finish line early photo 10

Workers work under the scorching heat at the construction site.

Dong Nai wants to use land recovered from Long Thanh airport project to build expressway
Dong Nai wants to use land recovered from Long Thanh airport project to build expressway

Proposal to add runway at Long Thanh 'super airport'
Proposal to add more runways at Long Thanh 'super airport'

Striving to complete Long Thanh airport 6 months ahead of schedule
Striving to complete Long Thanh airport 6 months ahead of schedule

Manh Thang



Source

Comment (0)

No data
No data

Same tag

Same category

Spreading national cultural values ​​through musical works
Elephant rider - a unique profession at risk of being lost
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product