The Vice Chairman of the Provincial People's Committee inspected the construction sites of the following projects: the road connecting Provincial Road 151 (Vo Lao, Van Ban) with the Noi Bai - Lao Cai Expressway (Cam Con, Bao Yen section); upgrading the road from Khanh Yen town to Liem Phu; the road to the center of Dan Thang commune; and Van Ban District General Hospital.

The leaders of Van Ban district reported to the Vice Chairman of the Provincial People's Committee on the construction progress, difficulties, problems and made proposals and recommendations to the province for each project.
Specifically, The project of connecting Provincial Road 151 (Vo Lao, Van Ban) with Noi Bai - Lao Cai Expressway (Cam Con, Bao Yen section) has a total investment of 115 billion VND. The scale of the project is a grade III mountainous traffic project, with a graded road surface structure.



The functional units have completed the statistics and counting of the current status of land recovery for 156 households in Vo Lao commune (Van Ban) and Cam Con commune (Bao Yen); issued decisions to recover 104 households and completed the dossiers and procedures for land recovery for the remaining households in the two communes. The construction unit has excavated the roadbed from Km1+00 to Km7+00, constructed horizontal drainage culverts, curb embankments from Km3+00 to Km7+00 and the underground spillway at Km1+121, reaching 35% of the volume according to the contract value.
The current difficulty is that during the implementation of the project to discover limonite iron ore, the unit has reported to the Ministry of Natural Resources and Environment for comments. On June 27, 2023, the Ministry of Natural Resources and Environment issued Document No. 4981/BTNMT-KSVN on the gathering, management and protection of minerals when implementing the project. In addition, there is a large bridge over Ngoi Nhu stream on the route, expected to go over the surface of the Vo Lao hydropower dam. However, Vo Lao Hydropower currently has no investment policy, so when the route is completed, it will not be open to traffic because there is no bridge over the stream.


The project to upgrade the road from Khanh Yen town center to Liem Phu has a total investment of 49 billion VND, with 492 affected households, and a total land acquisition area of more than 3.4 hectares. Currently, the project has constructed asphalt concrete on the road surface from Km1+259 to Km6+230 and some horizontal drainage culverts from Km2 to Km6+230. The unit is implementing the construction of the upper crushed stone foundation layer from Km 6+230 to Km 8+450. The volume has reached 50% of the contract value.
During the construction process, the relocation of electricity, water and telecommunications infrastructure occurred. Some locations had to adjust the route to suit the reality, and some construction items on the route had to be added to suit the current situation and improve the stability of the project. In addition, there was no consistency between the land clearance map and the cadastral map and the land use right certificate of the people, which had to be checked and adjusted, causing additional implementation time.


The road project to the center of Dan Thang commune has a total investment of more than 40.8 billion VND, the scale of a grade V mountainous road. Currently, 51/56 households in Dan Thang commune have agreed to the land clearance plan. For Hoa Mac commune, a price declaration has been made for 9 households; for the road section through Duong Quy commune, a meeting has been held to announce the compensation plan and make a plan for inventory. The cumulative value of the construction volume up to July 14, 2024 is about 3.32/33.22 billion VND, equivalent to 10% of the contract value.
The most difficult part of implementing this project is site clearance, because the project is implemented under the mechanism of people donating land and the State supports assets and crops on the land. Many households do not agree with the compensation plan according to state regulations.
The project to build a new Van Ban District General Hospital has a total investment of 200 billion VND, invested in building a grade II general hospital with a scale of 250 beds. The total construction volume reached 118,594 billion VND, equivalent to 80.6%, basically completed the main building and auxiliary buildings.
However, during the construction process, it was necessary to move 2 35KV power lines, which took a lot of time and affected the construction progress.


Based on the report of Van Ban district and the actual inspection of the site, comrade Nguyen Trong Hai, Vice Chairman of the Provincial People's Committee, requested Van Ban district to focus on reviewing and accurately assessing the problems with the site, and clarify the cause of the delay, whether it is due to the contractor or the site.
The Vice Chairman of the Provincial People's Committee requested the investor to direct the contractor to complete the work as it is done to facilitate the acceptance work; the supervision consultancy work needs more attention, strictly control the quality and progress of project implementation; the investor needs to rectify the contract management work, supervision consultancy work, and conduct surprise inspections of supervision consultancy records.
Close coordination is needed between localities with related projects, not leaving things to chance and citing difficulties and obstacles as excuses for delays.
Propose that Van Ban district synthesize all problems related to land clearance and report to the province for consideration and resolution in the spirit of construction as soon as land clearance is available, without delay, affecting the travel and life of people along the roads.
Closely monitor construction progress. If it is not guaranteed, we must have a decisive attitude, possibly adding subcontractors, and at the same time strictly punish contractors who violate contract progress.
On the same afternoon, comrade Nguyen Trong Hai, Vice Chairman of the Provincial People's Committee, inspected the construction site of basic construction projects in Bao Yen district (Lao Cai Newspaper will continue to inform).
Source
Comment (0)