Construction continues during September 2nd holiday to ensure progress of Rach Mieu 2 bridge

Việt NamViệt Nam06/09/2024


A representative of the My Thuan Project Management Board said that the unit arranged over 450 workers and technical staff to work during the September 2 holiday to ensure project progress and complete the Rach Mieu 2 Bridge (connecting Tien Giang and Ben Tre provinces) as planned.

ANH 2- BEN TRE - TR 8.jpg
Technical staff and workers increased to 3 shifts and 4 shifts to ensure the progress of Rach Mieu 2 bridge project.

Accordingly, at the Rach Mieu 2 Bridge construction investment project site, there are 32 construction teams, with 147 construction equipment and 80 technical staff. As of the end of August 2024, the Rach Mieu 2 Bridge project has been completed 57.73%, basically meeting the planned progress. According to the leader of the My Thuan Project Management Board, the units seriously implemented the construction in "3 shifts, 4 teams", determined to complete the project as directed by the Prime Minister and the Minister of Transport, striving to complete the project on the occasion of the National Day celebration on September 2, 2025.

PHAN HUY

Source: https://www.sggp.org.vn/thi-cong-xuyen-le-2-9-de-dam-bao-tien-do-cau-rach-mieu-2-post757308.html


Comment (0)

No data
No data

Same tag

Same category

Wind power field in Ninh Thuan: Check-in "coordinates" for summer hearts
Legend of Father Elephant Rock and Mother Elephant Rock in Dak Lak
View of Nha Trang beach city from above
Check-in point of Ea H'leo wind farm, Dak Lak causes a storm on the internet

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product