Vietnam.vn - Nền tảng quảng bá Việt Nam

Quang Nam is confused in the auction of sand from Co Co River.

Báo Kinh tế và Đô thịBáo Kinh tế và Đô thị18/03/2025


Auction failed

The project of dredging, emergency flood drainage and saltwater intrusion prevention of Co Co River was approved by Quang Nam province in 2018 and started in July 2020. In parallel with the project construction, the province assigned the Quang Nam Traffic Construction Investment Project Management Board (PMU) to coordinate with the departments to develop a plan to manage and collect materials after dredging (sand) to submit to the province for decision.

In July 2021, the Project Management Board was assigned by the People's Committee of Quang Nam province to organize the auction of 1,015,780 m3 of sand for pouring the foundation after dredging at the project. Specifically, about 767,510 m3 of sand after dredging was gathered at the site; about 523,270 m3 of undredged sand.

Sand left unused for many years is at risk of being wasted.
Sand left unused for many years is at risk of being wasted.

The Project Management Board has selected Quang Viet Joint Stock Auction Company to organize the auction. The auctioned assets are all dredged and undredged sand of the project with a starting price of VND 144,000/m3, according to Decision No. 2216/QD-UBND dated August 24, 2022.

However, after two announcements (from October 2022 to December 2022), no individuals or organizations registered to participate in the auction. The reason is that the volume of one-time auction is too large, after winning the auction, a large sum of money (about 200 billion VND) must be paid immediately.

In a recent submission, the Project Management Board said it had contracted with the consulting unit, FAC Company Limited - Central Branch, to determine the starting price. However, according to the Department of Finance, the price of VND144,000/m3 was approved a long time ago and is no longer suitable at the present time. Therefore, the consulting unit has organized a survey to determine the new starting price.

However, after many times of implementation, it is still not possible to determine because currently on the market there is no price information of similar materials as a basis for implementation. Therefore, the consulting unit proposed to terminate the contract because it is not possible to determine the starting price at the present time.

The Project Management Board also invited other consulting units in Quang Nam, Quang Ngai provinces and Da Nang city to determine the starting price, but no consulting unit registered to participate.

Divide into many lots to compete

Mr. Nguyen Van Thuong, Director of the Project Management Board, proposed that the Provincial People's Committee allow the application of the starting price approved by the Provincial People's Committee in 2022 at a price of VND 144,000/m3 to continue organizing the auction.

But first, only the volume of sand dredged and gathered at the site with a volume of 767,510m3 will be auctioned. Regarding the form, the province is requested to unify and divide it into many lots for auction. For the volume of sand that has not been dredged, about 523,270m3, the Board will coordinate with the Department of Agriculture and Environment to specifically advise the Provincial People's Committee to ensure compliance with regulations.

Quang Nam provincial leaders have repeatedly gone to the field and given instructions.
Quang Nam provincial leaders have repeatedly gone to the field and given instructions.

Previously, Vice Chairman of Quang Nam Provincial People's Committee Tran Nam Hung also agreed on the policy of dividing into many lots for auction. Urgently organize the auction for the volume of sand that has been dredged and gathered at the site. Assign relevant departments and branches to coordinate with the Project Management Board to advise the Provincial People's Committee to consider and handle undredged materials (sand) in accordance with regulations.

Also related to the dredged sand on Co Co River, Hoi An City People's Committee has submitted a document requesting the province to agree to allow the use of dredged sand to construct and repair the Tan Thanh coastal erosion (Cam An ward).

According to Hoi An City, the source of sand materials on the market is currently scarce and expensive. Therefore, the City proposes that the Provincial People's Committee and the Project Management Board consider and agree on the policy of allowing the use of sand dredged from the Co Co River to reinforce coastal erosion with a volume of about 3,000 m3.



Source: https://kinhtedothi.vn/quang-nam-lung-tung-trong-viec-dau-gia-cat-song-co-co.html

Comment (0)

No data
No data

Same tag

Same category

Tombs in Hue
Discover the picturesque Mui Treo in Quang Tri
Close-up of Quy Nhon port, a major commercial port in the Central Highlands
Increasing Hanoi's attractiveness from flower tourism spots

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product