Vice Chairman of the Provincial People's Committee Nguyen Trong Hai inspected the progress of the basic construction investment project in Bao Yen district.

Việt NamViệt Nam14/07/2024

At the meeting, the leaders of the Provincial Traffic Construction Investment Project Management Board reported on the progress of the Project to Upgrade Provincial Road 160, from Vinh Ha Hydropower Plant (Tan Duong Commune) to National Highway 279 (Km29 - Km34) in Xuan Hoa Commune and the Project to Upgrade Provincial Road 160, from National Highway 279 (in Xuan Hoa Commune) to Xuan Thuong (Km41 - Km63).

by 5.jpg
Working scene.

The Project to Improve and Upgrade Provincial Road 160, from Vinh Ha Hydropower Plant (Tan Duong Commune) to National Highway 279 (Km29 - Km34) in Xuan Hoa Commune has a total investment of 30 billion VND, with a total length of 5.26 km, invested by the Provincial Traffic Construction Investment Project Management Board. For this project, functional units have counted and priced 68/72 households in the area of ​​site clearance. The contractor has completed the construction of precast components, arranged at 11/11 culvert locations, 2/4 embankment locations, 2/4 km of roadbed, 1.8/4 km of type II crushed stone roadbed and 1.2/4 km of type I crushed stone roadbed. The construction and installation value is about 29%.

by 3.jpg
Leaders of the Provincial Traffic Construction Investment Project Management Board reported on the progress of projects invested in Bao Yen district.

Project to renovate and upgrade Provincial Road 160, from National Highway 279 (in Xuan Hoa commune) to Xuan Thuong (Km41-Km63). The project has a total investment of 138 billion VND, invested by the Provincial Traffic Construction Investment Project Management Board. In 2024, the capital allocated for the project is 40 billion VND. The disbursement value as of June 30, 2024 is 29.4/40 billion, reaching 73.5%. Regarding the project implementation progress, in package No. 13, the construction of the project was won by the joint venture of Vu Thanh Company Limited - Joint Stock Company 873 (Hanoi) - Lao Cai Construction and Inspection Joint Stock Company, with a value of over 103 billion VND. Up to now, the units have completed 26% of the volume and value. Contractors are currently constructing the roadbed from Km41 to Km44; installing D100 circular culvert systems at some locations; completing retaining walls on positive and negative slopes; constructing Mai Thuong bridge;...

by 1.jpg
Vice Chairman of the Provincial People's Committee inspected the field of the Project to Upgrade Provincial Road 160 from Vinh Ha Hydropower Plant to National Highway 279 (Km29 - Km34).

The leader of the Provincial Traffic Construction Investment Project Management Board said that the two projects had difficulty in ensuring construction progress due to slow site clearance. The reason was that the land plots of some households overlapped between forest land and other types of land, so the Bao Yen District Land Registration Office had not yet extracted them to issue a notice of land recovery; some households had not yet completed land inheritance procedures. In addition, because the assets and trees of some households were located on land along the road traffic corridor, land managed by the Commune People's Committee, river and stream land, it was difficult for the owners to prepare site clearance records, and it took a long time to verify and confirm the time of asset creation and land origin; many households said that the compensation value was not reasonable. On the other hand, the weather in June and early July 2024 was rainy, affecting the plan to pave asphalt concrete roads.

by 4.jpg
Vice Chairman of Bao Yen District People's Committee Nguyen Van Nhat reported on the progress of projects and site clearance work.

At the meeting, the leaders of Bao Yen District People's Committee reported on the construction progress of the Project to Upgrade and Renovate Provincial Road 160, from Hanh Phuc Bridge (Pho Rang Town) to Xuan Thuong Commune People's Committee and the Project to Upgrade the Inter-Commune Road, from Xuan Thuong Commune connecting with Provincial Road 160 to Viet Tien Commune; Bao Yen District General Hospital Project.

by 6.jpg
by 7.jpg
Working group inspected Bao Yen District General Hospital Project.

The leaders of the district People's Committee shared that the current difficulties and problems are site clearance; some households have not agreed, causing obstacles, leading to some sections of the route not ensuring construction progress.

1. Project to upgrade and renovate Provincial Road 160, section from Hanh Phuc Bridge (Pho Rang town) to Xuan Thuong Commune People's Committee:

- Total investment: 14.3 billion VND.

- Scale: upgrade and open a new route with a main route length of 1.2 km. The starting point connects with the Hanh Phuc bridgehead and Provincial Road 160 at Km36+253.46 in the current direction to Xuan Hoa. The end point connects with Provincial Road 160 at Km37+483 in the direction to Xuan Thuong Commune People's Committee.

- Implementation progress: the estimated construction volume is 60% of the contract, including drainage items, roadbed (including approved additional volume) of the section without route adjustment. Currently, we are waiting for completion of site clearance of the adjusted section and locations that need additional funding for synchronous construction.

2. Project to upgrade inter-commune road, from Xuan Thuong commune connecting with Provincial Road 160 to Viet Tien commune:

- Total investment: 20 billion VND.

- Scale: upgrading and renovating a route with a length of 3.99 km; 1 permanent reinforced concrete and prestressed concrete bridge with 1 simple span, span length 33 m.

- Implementation progress: the project is implemented in the form of State and People working together. Up to now, 4.7/4.99 km of land has been cleared; construction has been completed for sections that do not require design adjustment.

3. Bao Yen District General Hospital Project:

- Total investment: 235 billion VND.

- Scale: building a 3-5 storey medical examination and treatment building, with a scale of 250 beds and other ancillary items.

- Implementation progress: The project has been approved by the Provincial People's Committee for 4 construction and equipment supply and installation packages. Package No. 7A (construction of building blocks) is expected to be completed and handed over in December 2024. Package No. 7B (construction of leveling, electricity, water supply, outside and auxiliary items) is expected to be handed over in October 2024. Package No. 8 (construction of air conditioning for the block house, supply and installation of elevator equipment, air conditioning equipment for the block house) is expected to be completed in November 2024. Package No. 9 (supply and installation of medical waste incinerator equipment, 200 wastewater treatment plant) has not yet organized contractor selection.

Bao Yen District People's Committee requests the Provincial People's Committee to pay attention and promptly approve the adjustment of the technical economic report as a basis for continuing to carry out site clearance work; adjust the contractor selection plan for the additional work after the investor has approved the design adjustment and addition.

DSC_6702.JPG
Vice Chairman of the Provincial People's Committee Nguyen Trong Hai gave a speech at the meeting.

At the meeting, Vice Chairman of the Provincial People's Committee Nguyen Trong Hai exchanged information and directed the removal of difficulties and obstacles in the implementation progress of each basic construction investment project.

The Vice Chairman of the Provincial People's Committee requested relevant departments, branches, Bao Yen District People's Committee and investors to review the construction progress of the entire project; ensure equipment, materials and human resources are available in time to ensure the construction progress is on schedule.

Units and localities should focus on doing a good job of site clearance, promptly removing difficulties and obstacles; flexibly implementing solutions to propagate and mobilize people in compensation work and spreading the value of new routes, which will create an important lever in socio-economic development.

The Vice Chairman of the Provincial People's Committee requested that investors direct contractors to complete construction as soon as the site is available, and contractors who are behind schedule will be severely punished.

For each project, the Vice Chairman of the Provincial People's Committee set a specific time frame to resolve compensation and site clearance issues; requested units and localities to be determined to complete the assigned tasks and requirements.


Source

Comment (0)

No data
No data

Same tag

Same category

Vietnamese artists and inspiration for products promoting tourism culture
The journey of marine products
Explore Lo Go - Xa Mat National Park
Quang Nam - Tam Tien fish market in the South

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product