Thieu Giang Interchange is the 7th intersection on the North-South Expressway through Thanh Hoa province and is entering the road paving phase, preparing to be completed and put into use on April 30.

Nút giao thứ 7 trên cao tốc Mai Sơn - QL45 đoạn qua Thanh Hóa sẽ hoàn thành vào dịp 30/4- Ảnh 1.

Thieu Giang intersection is the 7th intersection on the Mai Son - National Highway 45 through Thanh Hoa province.

In late March 2023, it was observed at the construction site that many groups of mechanics and bridge workers were working hard. At the intersection, there are 4 branches leading to and from the highway that have been paved with the first layer of asphalt by the construction unit, and many locations have been paved with the second layer. At this intersection, there is a flyover over the highway that is also being welded by workers of Phuong Thanh Traffic Construction Investment Joint Stock Company, preparing to pour the bridge railing.

Nút giao thứ 7 trên cao tốc Mai Sơn - QL45 đoạn qua Thanh Hóa sẽ hoàn thành vào dịp 30/4- Ảnh 2.

Worker Pham Van Giap is checking the wall measurements to prepare to pour the bridge railing.

While holding a ruler to measure the width of the partition wall in preparation for pouring concrete, worker Pham Van Gioi (55 years old, residing in Yen Dinh district, Thanh Hoa province) shared: Since the construction of this overpass started, we have encountered many difficulties because the bridge has to be built with beams across the highway. If we are not careful, it will greatly affect the vehicles passing under the bridge. In addition to having a protective net, when working above, we have to be very careful not to let materials, even tiny stones, fall onto the highway.

Worker Luong Van Que (45 years old, from Hoang Hoa district) said: We start working from 6am to almost 11am, and in the afternoon from 1:30pm to 5:30pm. Because there is no electricity in this area, we cannot work at night, but we can only work 2 hours more during the day. There are only about 70m left to finish welding the walls to pour concrete for the bridge railing.

Nút giao thứ 7 trên cao tốc Mai Sơn - QL45 đoạn qua Thanh Hóa sẽ hoàn thành vào dịp 30/4- Ảnh 3.
Nút giao thứ 7 trên cao tốc Mai Sơn - QL45 đoạn qua Thanh Hóa sẽ hoàn thành vào dịp 30/4- Ảnh 4.

Thieu Hoa District Construction Investment Project Management Board said that the output up to now has reached 84%.

Not far away, at the exit of the expressway interchange, Mr. Nguyen Duc Thao, Construction Site Manager of Factory 11, a contractor of the Central Joint Stock Corporation, is directing the concentration of machinery to prepare the second layer of asphalt.

"Since the beginning of the year, the rainy weather has affected the road paving. Taking advantage of the sunny days, we have to mobilize more manpower and machinery to do the work. At our construction site, there are 4 engineers and about 20 workers. We only have 14 days left to finish the road paving and then turn to traffic safety items to open the road to traffic on April 30," said Mr. Thao.

Nút giao thứ 7 trên cao tốc Mai Sơn - QL45 đoạn qua Thanh Hóa sẽ hoàn thành vào dịp 30/4- Ảnh 8.

According to plan, Thieu Giang intersection will be completed and put into use on April 30.

Talking to Giao thong Newspaper, Mr. Ngo Khac Dao, an officer of the Thieu Hoa District Construction Investment Project Management Board, said: The output of Sub-project 2 (the road connecting National Highway 1 with National Highway 45 invested by the People's Committee of Thieu Hoa District, Thanh Hoa) reached 84% of the plan. Currently, the construction of the second end of the expressway overpass, guardrails, expansion joints, and asphalt concrete is underway. All of this is contained in just 15 days to complete the road surface to do the next items such as road markings, lighting, traffic safety systems, and put the project into use soon on the occasion of April 30.

It is known that the project connecting National Highway 1 with National Highway 45 has a length of 14.6km with a total investment of 1,417 billion VND and is divided into 3 component sub-projects.

Of which, Sub-project 1 (Ma River overpass and road at both ends of the bridge from Km 5+250 - Km 7+250) has a total investment of 655 billion VND from the provincial budget, invested by Thanh Hoa Traffic Construction Investment Project Management Board. Sub-project 2 is invested by Thieu Hoa District People's Committee.

Sub-project 3, the road section on Hoang Hoa district side (Km0 - Km 5+250) is 5.25km long with a total investment of 307 billion VND, invested by Hoang Hoa district People's Committee.

The North-South expressway in the east passing through Thanh Hoa province is over 98km long, divided into 3 component projects: Mai Son - QL45; QL45 - Nghi Son and Nghi Son - Dien Chau.

On the entire expressway through Thanh Hoa province, there are 7 planned interchanges, including: Gia Mieu interchange (Km 295+800); Ha Linh interchange (Km 306+000); Thieu Giang interchange (Km 315+380); Dong Xuan interchange (Km 327+142); Dong Thang interchange (Km 335+400); Van Thien interchange (Km 351+320) and Nghi Son interchange (Km 379+500).

Thieu Quang Interchange is a part of Sub-project 2 - Highway connecting project QL1 with QL45 invested by Thieu Hoa District People's Committee (Thanh Hoa Province). Thieu Giang Interchange intersects with Mai Son - QL45 expressway at Km 315+380.



Source

Comment (0)

No data
No data

Same tag

Same category

Increasing Hanoi's attractiveness from flower tourism spots
International Music Festival 'Road To 8Wonder - The next icon'
Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product