Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7

Việt NamViệt Nam03/08/2024


Nghe An:

TPO – After nearly 2 years of construction, all 3 packages of the project to upgrade and expand National Highway 7 from Km0-Km36 through Nghe An are still unfinished and at risk of "breaking" the schedule due to problems in site clearance.

Close-up video of National Highway 7A (Nghe An) at risk of "flooding" progress due to site clearance problems.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 1

Project Management Board 4 has reported on the implementation of the project to upgrade National Highway 7, section Km0-Km36, and to handle landslides caused by storms and floods in the Khe Thoi - Nam Can section. Accordingly, up to now, this project has not been completed as planned.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 2

The project to upgrade National Highway 7, section Km0-Km36, and handle landslides caused by storms and floods in the Khe Thoi - Nam Can section was approved by the Ministry of Transport on March 18, 2022 and officially started construction in September 2022. The project has a total investment of over VND 1,300 billion with a total length of 27.5km passing through Dien Chau, Yen Thanh and Do Luong districts of Nghe An province.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 3
The project is divided into 3 construction packages 01, 02 and 03. Of which, package 02 is expected to be completed in July 2023 to connect with the Nghi Son - Dien Chau expressway project; the remaining 2 packages are to be completed in 2024. However, by July, all 3 construction packages have not yet reached the finish line, of which package 01 reached 72.6%, package 02 reached 69.5%, package 03 reached 79.1%.
Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 4Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 5

There are many reasons why the packages cannot be completed. However, the main reason is that the project is still stuck with land clearance on the route. The land is not handed over continuously, causing the construction to be unfinished.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 6

According to the report, by mid-July, Yen Thanh, Do Luong, and Dien Chau districts had handed over 52.84km/55.4km of land, reaching 95.37% of the left and right routes. Many households have not yet agreed to compensation to hand over the land to the construction unit.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 7

The railway overpass in Dien Phuc commune, Dien Chau district cannot be completed due to land acquisition problems.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 8

The bridge is not yet completed, the road surface is narrow and right at the intersection with the railway, causing traffic congestion here.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 9

A narrow section of old National Highway 7 through Hamlet 8, Vien Thanh Commune (Yen Thanh District) cannot be upgraded or expanded.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 10Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 11

The slow and unfinished construction has greatly affected the lives of people living along the road and vehicles on the route. Every time a vehicle passes by, dust flies everywhere.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 12

Project Management Board 4 (Ministry of Transport) said that this unit has sent a report to the People's Committee of Nghe An province and proposed that the province direct functional agencies and localities to hand over the remaining sections of the project no later than July 2024. For households that obstruct, oppose, and are not eligible for compensation, it is recommended that the district authorities organize construction protection no later than July this year.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 13

However, by August 2024, the land on the route has not been handed over to continue construction to complete the project. Talking to PV Tien Phong , Mr. Nguyen Van Duong - Vice Chairman of Yen Thanh District People's Committee - said that there are still 50 households in the district that have not agreed to hand over the land to implement the construction of National Highway 7. Mr. Duong said that the district has developed a construction protection plan and is waiting for the competent authority to appraise it for implementation.

Risk of 'breaking' progress of trillion-dollar project to 'upgrade' National Highway 7 photo 14
It is known that the Ministry of Transport has extended the deadline for the bid packages to be completed in November. With the current situation, the bid packages are unlikely to achieve the expected progress.

Ngoc Tu

Source: https://tienphong.vn/nguy-co-vo-tien-do-du-an-nghin-ty-len-doi-quoc-lo-7-post1660097.tpo


Comment (0)

No data
No data

Same tag

Same category

Spreading national cultural values ​​through musical works
Elephant rider - a unique profession at risk of being lost
Lotus color of Hue
Hoa Minzy reveals messages with Xuan Hinh, tells behind-the-scenes story of 'Bac Bling' causing global fever

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product