The Ring Road 4 – Capital Region project passes through Dan Phuong district with a length of 6km, the total area recovered for the project is 72.4ha. Of which, the land area that does not need to be cleared (rivers, dykes) is 7.78ha. The land area that needs to be cleared is 64.62ha.
People of Hong Ha commune (Dan Phuong district) receive compensation to support site clearance for Ring Road 4 - Capital Region. Photo: HNM
The total number of graves that must be moved to implement the project is 1,678 graves.
Regarding compensation and support for site clearance, the People's Committee of Dan Phuong district has issued 1,209 decisions approving compensation and support plans, with a total amount of VND 457.88 billion.
The total amount of money paid so far is 453.63 billion VND, of which 1,199 households were paid a total of 447.7 billion VND, the project site clearance area is 40.0 hectares of agricultural land, reaching 99.33% and 5.93 billion VND for households moving graves.
Regarding residential land, the total number of recovered land plots is 112 plots (120 households), with an area of 1.93 hectares. The district has issued 106 notices of land recovery for 106 households, with an area of 1.62/1.93 hectares, reaching 83.5%; there are 14 plots that have not yet issued notices of land recovery for 6 households in Hong Ha commune, with an area of 0.32 hectares.
The total area cleared is 70.3/72.4ha of the entire project area, reaching 97.1%.
Dan Phuong District strives to complete 100% of the site clearance for the Ring Road 4 - Capital Region Construction Project by December 31, 2023, and hand it over to the investor. The work of moving graves to the cemetery is guaranteed to be on schedule.