Today, March 6, the Economic - Budget Committee of the Provincial People's Council worked with the Provincial Economic Zone Management Board on the results of allocation, management, use of capital sources and progress of implementation of projects and basic construction investment works in 2024 (cumulatively up to the end of 2023) approved by the Provincial People's Council in Resolution No. 69/NQ-HDND dated August 4, 2023; Resolution No. 111/NQ -HDND dated December 7, 2023; Resolution No. 132/NQ -HDND dated December 19, 2023 of the Provincial People's Council assigned by the Provincial People's Committee to localities and units to manage projects or act as investors. Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang attended the meeting.
According to the report of the Provincial Economic Zone Management Board, in Resolution No. 111, there are projects such as: Road connecting Dong Nam Quang Tri Industrial Park to Cua Viet Port. Up to now, the project has package No. 10 which has been allocated enough capital but is still stuck in site clearance work so it cannot continue to be implemented.
The Economic - Budget Committee of the Provincial People's Council conducted a field survey of the My Thuy Port project - Photo: HA
The project of leveling and technical infrastructure in the central area of La Lay border gate was approved with a total investment of 108 billion VND, the implementation period is from 2021-2024, currently completed items, the leveling part of the waiting area with an area of 0.95 ha is waiting for a license to conduct mass blasting from the General Department of Defense Industry and is expected to be deployed in the second half of March 2024.
The feasibility study report of the RD 01 and RD 04 projects in Quan Ngang Industrial Park was approved by the Provincial People's Committee in Decision No. 3183/QD-UBND dated December 25, 2023 with a total investment of 25 billion VND, implementation period from 2023-2025. Due to capital allocation at the end of 2023, the project has only disbursed consulting costs and other investment preparation costs.
In Resolution No. 132, there are 2 projects adjusting the capital reduction of the medium-term plan for 2021-2025: the project of clearing bombs and explosives in the resettlement areas of Trieu Phong and Hai Lang districts; the project of the resettlement area of Hai Khe commune and the road to the resettlement area (phase 1). These 2 projects have been completed and the project settlement has been finalized, so the medium-term capital has been adjusted to decrease according to the completed value.
Regarding the implementation of some projects (not using public investment capital) in industrial parks and economic zones in the province such as: My Thuy Port Project, up to now there are still some difficulties and problems related to the dossier of handing over the sea area, the location of dumping dredged material and using dredged material, the exploitation of planted forest wood, the plan to dredge water areas, ship turning basins, mineral recovery within the project scope, site clearance, resettlement...; the project of Investment in construction and business of infrastructure of Trieu Phu Multi-industry Industrial Park, up to now, the procedures for establishing the industrial park and dossiers for changing the purpose of forest use have been basically completed.
Land use planning and planning...; Quang Tri Industrial Park project, up to now, the site clearance work in some areas (about 1.9 ha) has issued a decision approving the compensation and support plan but the people still do not agree, the wastewater discharge point of the project is outside the scope of the project implementation, so there are problems in granting construction permits that do not ensure the prescribed conditions, the construction progress of water supply works for the project is slow, affecting the investment activities in building technical infrastructure and attracting investment of investors...
The project of investing in construction and business of infrastructure of Tay Bac Ho Xa Industrial Park, up to now, the site clearance work has encountered certain difficulties and obstacles. Although the investor has made great efforts to coordinate with departments, branches and localities to resolve them, it was not until mid-2023 that the difficulties and obstacles were basically resolved, which has affected the progress of project implementation...
The Provincial Economic Zone Management Board has proposed to the Economic - Budget Committee of the Provincial People's Council issues related to basic construction investment projects/works in 2024 (cumulatively until the end of 2023) approved by the Provincial People's Council in the above resolutions such as: Strengthening land management and use in localities; considering and periodically adjusting unit prices of architectural objects and crops in accordance with reality; focusing on solving site clearance, compensation, and resettlement support; updating and adjusting the announcement of construction material prices and construction price indexes to meet the requirements of construction investment cost management; controlling fluctuations in construction material prices and strictly handling acts of speculation and price hikes for profit.
Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang requested the Provincial Economic Zone Management Board to proactively coordinate closely with departments, branches, sectors and localities to do a good job of site clearance; focus human resources to completely resolve problems to ensure the progress of project implementation. There should be a specific plan on the location of dumping dredged material and the use of dredged material to release the volume of waste for the My Thuy Port Area project.
Regarding the recommendations, the Economic - Budget Committee of the Provincial People's Council will take note, consider and recommend to competent authorities for resolution in the coming time.
On this occasion, the Economic - Budget Committee of the Provincial People's Council visited the field to survey the projects: Investment in construction and business of infrastructure of Trieu Phu Multi-industry Industrial Park, My Thuy Port Area, Construction of technical infrastructure of resettlement area serving the Southeast Quang Tri Economic Zone.