On the morning of May 23, at the online conference of the Government Standing Committee with localities implementing the 500kV line project circuit 3 (500KV project) from Quang Trach (Quang Binh) to Pho Noi (Hung Yen), Mr. Do Trong Hung, Secretary of Thanh Hoa Provincial Party Committee, reported on the progress of site clearance and handover for the implementation of this important project.
Accordingly, the 500kV transmission line project in Thanh Hoa has 299 column foundation locations and 138 anchorage areas (KN). As of May 24, only one KN in Tan Truong commune, Nghi Son town is still stuck with land procedures and cannot be handed over.
At the online conference, Thanh Hoa provincial leaders pledged to complete site clearance and hand over this project before May 30, 2024. At the same time, Thanh Hoa identified this as a key national project, so although the locality has a large number of column locations and anchorages, Thanh Hoa has been very active and determined to complete and hand over the project on schedule and create the best conditions for the contractor to implement the project.
On May 24, in a quick exchange with Nguoi Dua Tin, a leader of Nghi Son town said that there is still a piece of land that has not been handed over to an elderly household, and there are some problems with land procedures. Currently, the locality is actively mobilizing, persuading and trying to create the best conditions for people to understand and agree. At the same time, the town has also prepared a plan to soon complete the handover of the land for the project before May 30, ensuring electricity is turned on before June 30 according to the direction of the Prime Minister and the People's Committee of Thanh Hoa province.
National key project
According to the report of Vietnam Electricity Group, by May 22, 2024, a total of 4 projects in the 500kV Line Project, circuit 3, from Quang Trach to Pho Noi, had handed over 1,177/1,177 (100%) of the pole foundation locations and 478/513 anchorage spaces (KN), with 35/513 KN not yet handed over.
Currently, localities and contractors have been focusing on implementing construction, working "3 shifts, 4 crews", 24/7. At the same time, regularly checking and urging the production and supply of steel columns at factories manufacturing materials related to the project.
To complete the project's energization according to the schedule assigned by the Prime Minister, Vietnam Electricity Group is urgently urging construction contractors to focus on human resources and construction machinery, promptly complete the construction of column foundations, pole erection, and wire stretching according to the committed schedule, striving to test, accept, and energize from June 20 to 30, 2024.
Speaking at the 500kV line 3 project, Prime Minister Pham Minh Chinh praised the drastic participation of ministries, branches, and local authorities at all levels; the support of the people; the efforts of Vietnam Electricity Group, the National Power Transmission Corporation, and the determination of contractors to overcome difficulties in construction to ensure the project's progress and quality.
Emphasizing the role of the national key project, the Prime Minister requested Vietnam Electricity Group to review and rebuild the progress critical path, strive to complete the wire pulling by June 20, 2024 and be determined to energize before June 30, 2024.
With the determination to "work, not retreat", the Prime Minister requested relevant ministries, branches and units according to their functions and tasks to make greater efforts and determination, and implement solutions to speed up project progress.
The leaders of relevant localities continue to lead, direct, inspect, urge, and coordinate the implementation of the project; ensure the site for construction and wire pulling; ensure the legitimate interests of people and businesses in the area where the line passes. Contractors continue to strive to overcome all difficulties, ensure project progress, quality, safety and environmental sanitation, and are determined to bring the project to the finish line before June 30, 2024.
Viet Phuong