Contractors constructing the storm shelter for fishing boats in Co To island district (Quang Ninh) are working through the night with the determination to finish on schedule.
Construction crews work through the night
On the afternoon of December 7, although it was a weekend, on the route connecting the fishing logistics service area with the route leading to Co To wharf, large trucks were still busy transporting soil and rocks for leveling; rollers and graders quickly leveled the ground.
Up to now, the embankment system along the road has been completed, the road surface has been rolled and compacted about 2/3.
The route connecting Co To port to the wharf is gradually coming into existence.
Next to the road is the dike project to protect the water area, which has also taken shape with a length of about 100m.
In the area where components are cast for the construction of the breakwater, machinery, equipment and human resources are also fully mobilized.
Located on the other side of the big Co To island, the Truong Xuan anchorage and docking area in Dong Tien commune, the construction directions and points are also being rapidly deployed by contractors. Standing on the far shore, one can see the cranes on barges diligently dredging the shipping channel, water area and digging the foundation.
The construction atmosphere is urgent at the site, deploying 3 shifts and 4 crews to speed up progress.
Mr. Luong Van Phong, a road roller driver for Sa Vi Consulting and Construction Joint Stock Company, the construction unit of the shared road, said that Phong is from Dien Bien and has been working on the island for more than a month. Seeing his fellow drivers working hard day and night, Phong also tried to keep up with his colleagues.
"Before coming here, I worked on a project inland, so I haven't been home for 4 months. Although I miss my family, the contractor's overtime policy is very good, so I decided to focus on working so that I can come home during Tet to take care of my family," Phong boasted.
Mr. Vu Van Phap, an officer of the Field Laboratory of the Civil and Industrial Construction Consulting Joint Stock Company, is carrying out technical operations with his colleagues to serve the construction and said: The contractor works day and night, and the testing department is always on site to ensure progress.
Panoramic view of Co To fishing port with many shortcomings, causing ships and boats to have to move elsewhere every time there is a storm or strong wind.
Mr. Nguyen Minh Phuong, an officer of the Project Management Department (PMD) under the Project Management Board for Investment and Construction of Agricultural and Rural Development Works (PMB) of Quang Ninh shared that this is the construction area of the Storm Shelter Anchorage Area project for fishing boats in Co To island district.
The project has two components: Co To port area and Truong Xuan anchorage area. In this area, 42% of the wave-breaking items have been completed, 27% of the mooring buoys have been completed, and 63.5% of the road connecting to Co To wharf has been completed.
The area of Truong Xuan lagoon is 48.49 hectares with a dredging volume of 1.15 million m3. Here, contractors are arranging 1 dredger, 4 sand suction vessels, 2 grab buckets, 2 rock transport barges, 1 bottom discharge barge, 2 concrete deck excavators... As a result, 37.3% of the project's workload has been achieved.
"At this time, the weather is favorable, so contractors are focusing on maximizing human resources and equipment to work in 3 shifts and 4 teams to speed up the construction progress. The project will be implemented in 24 months, starting in early December 2023. With the current construction speed, the project will definitely be completed on schedule," Mr. Phuong shared.
Strive to bring the project to the finish line
It is known that the project of Fishing Boat Anchorage Area in Co To has been approved by the Ministry of Agriculture and Rural Development with a total investment of nearly 660 billion VND, of which the central budget capital is nearly 500 billion VND, and the Quang Ninh provincial budget capital is nearly 160 billion VND.
The contractor is preparing all components to serve the construction of the breakwater at Co To fishing port.
The project started construction on December 6, 2023, with a regional storm shelter area, meeting the anchoring needs of 1,200 fishing vessels with a capacity of up to 800CV.
The project includes the following items: Co To port area accommodates 360 ships from 90-800CV; construction of a breakwater in the North; a connecting road from the port to the fishing logistics service area; Truong Xuan lagoon area accommodates 840 ships from 200CV or less; construction of boarding and disembarking points for fishing boats; connecting roads; and a channel to the anchorage area.
Mr. Pham Phuc Quang, Director of the Quang Ninh Agricultural and Rural Development Construction Investment Project Management Board - the project investor, said that during the project implementation, the unit closely coordinated with Co To district to discuss and advise superiors to immediately remove difficulties and problems, if any arise.
"Currently, we are always closely following the site to urge the contractor, focus on human resources and machinery to take advantage of favorable weather to implement construction items, striving to complete the project on time," said Mr. Quang.
Source: https://www.baogiaothong.vn/xuyen-dem-dua-du-an-khu-neo-dau-tau-ca-o-co-to-ve-dich-192241204192239097.htm
Comment (0)