The 7.7km Ham Kiem - Tien Thanh route connecting Phan Thiet - Dau Giay expressway to Binh Thuan coastal road has just officially opened to traffic, surprising many tourists because of the shortened journey and beautiful scenery.
The Ham Kiem - Tien Thanh road project from National Highway 1 to the coastal road DT719B through Phan Thiet City and Ham Thuan Nam District (Binh Thuan) started construction in November 2021 and is expected to open to traffic in October 2023. The total investment capital is about 400 billion VND. However, due to land acquisition problems, the project's progress has been delayed many times.
When completed, this road section will connect to National Highway 1 at Ba Bau intersection to Phan Thiet - Dau Giay Expressway and connect to coastal road DT719B, connecting residential areas, coastal tourist areas and La Gi town.
Source: https://www.baogiaothong.vn/thong-xe-duong-noi-cao-toc-phan-thiet-dau-giay-ra-bien-o-binh-thuan-192250124150226131.htm