Vietnam.vn - Nền tảng quảng bá Việt Nam

Speeding up construction of 120 billion VND bridge in Vu Quang

(Baohatinh.vn) - Due to the efforts of the construction, at this time, the Hop Chuoi bridge project (Vu Quang town, Ha Tinh) has reached more than 75% of the volume, expected to be completed before June 30, 2025 (6 months ahead of schedule).

Báo Hà TĩnhBáo Hà Tĩnh02/04/2025

bqbht_br_img-8443-copy.jpg
Hop Chuoi Bridge Project (Vu Quang town) is of special importance in completing the town's traffic infrastructure according to the approved planning, serving people's needs, promoting socio-economic development, and trade of goods in the district.
bqbht_br_img-2861-copy.jpg
The project has a total investment of 120 billion VND, constructed by Hoang Ngoc Construction and Trading Company Limited (Huong Khe). Started on December 20, 2023, the project is expected to be completed before June 30, 2025 (6 months ahead of schedule).
bqbht_br_img-2877-copy.jpg
Identifying the role and importance of the project, since the start of construction, the working atmosphere at the construction site has always been urgent and serious.
Cầu Hốp Chuối được thiết kế với 5 nhịp chiều dài 178m, rộng 7m. Anh Nguyễn Đình Anh - Chỉ huy trưởng của Công ty TNHH Xây dựng và Thương mại Hoàng Ngọc cho biết: "Nhờ nỗ lực thi công nên tới thời điểm này, dự án đã đạt 75% khối lượng. Cụ thể, đã thi công được 25/30 dầm, hoàn thiện thi công mố M1 và các trụ T1, T2, T3. Ngoài ra, đơn vị cũng đã thi công đường hai đầu cầu đạt 70% khối lượng, với chiều dài 2/2,7km).
Hop Chuoi Bridge is designed with 5 spans, 178m long and 7m wide. Mr. Nguyen Dinh Anh - Commander of Hoang Ngoc Construction and Trading Company Limited said: "Thanks to the construction efforts, up to now, the project has reached 75% of the volume. Specifically, 25/30 girders have been constructed, pier M1 and pillars T1, T2, T3 have been completed. In addition, the unit has also constructed the roads at both ends of the bridge, reaching 70% of the volume, with a length of 2/2.7km).
Nhà thầu đang tập trung huy động máy móc, nhân lực, vật tư, vật liệu tối đa để thi công hoàn thành công trình theo tiến độ đề ra.
The contractor is focusing on mobilizing maximum machinery, human resources, supplies and materials to complete the project according to the set schedule.
bqbht_br_img-8438-copy.jpg
Mr. Nguyen Van Son - a construction worker at the site said: "Determining the importance of the project, we always closely follow the tasks we undertake. Construction in river conditions has certain difficulties, but we always focus highly, put quality first and commit to constructing according to the design documents. With the efforts of the unit, we hope that Hop Chuoi bridge will be completed before June 30."
bqbht_br_img-8434-copy.jpg
Determining that the project completion time is running out, Hoang Ngoc Construction and Trading Company Limited is focusing on adding more machinery and human resources, increasing 7 excavators, 2 drills and 3 cranes along with more than 40 workers and construction technicians to ensure the set progress.
bqbht_br_img-8432-copy.jpg
Hop Chuoi Bridge is expected to open up new development space for Vu Quang town.
bqbht_br_img-8444-copy.jpg
Mr. Tran Van Binh (resident of residential group 1, Vu Quang town) excitedly said: "The Hop Chuoi bridge project will facilitate travel, contributing to the socio-economic development of the locality. With the attention and close direction of authorities at all levels, along with the efforts of the construction unit, hopefully, the Hop Chuoi bridge project will be completed soon, bringing practical values ​​to the community."

Hop Chuoi Bridge is an important project, when completed it will facilitate travel and economic trade of local people. To ensure the progress and quality of the project, the unit has directed and urged the contractor to overcome all difficulties, taking advantage of the weather to speed up the progress of the items. At the same time, assigning staff to regularly stay at the construction site, promptly handling problems, and encouraging staff and workers to achieve the highest efficiency.

Mr. Nguyen Truong Tho - Director of Vu Quang District Construction Investment Project Management Board

Video: Shape of Hop Chuoi bridge in Vu Quang town.

Source: https://baohatinh.vn/tang-toc-thi-cong-cau-120-ty-dong-o-vu-quang-post285180.html


Comment (0)

No data
No data

Same category

Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration
U90 veteran causes a stir among young people when he shares his war story on TikTok
Moments and events: April 11, 1975 - The battle in Xuan Loc was fierce.

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product