Vietnam.vn - Nền tảng quảng bá Việt Nam

Nghe An has disbursed total public investment capital of more than 4,979 billion VND, reaching 47.04%.

Việt NamViệt Nam26/09/2023

On the morning of September 26, comrade Nguyen Duc Trung - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee chaired the regular meeting of September 2023 of the Provincial People's Committee.

bna_IMG_5217.jpg
Overview of the regular meeting of the Provincial People's Committee in September 2023. Photo: Pham Bang

Reporting on the implementation of the public investment plan in the first 9 months of 2023, Director of the Department of Planning and Investment Pham Hong Quang said that the total concentrated public investment plan in 2023 is 7,134.628 billion VND; of which the plan for 2023 is 5,583.8 billion VND, the extended plan for 2022 is 1,550.828 billion VND; to date, the detailed allocation to each unit for implementation has been basically completed.

To speed up the disbursement of public investment capital, the Provincial People's Committee promptly issued documents to direct the implementation of public investment capital disbursement in the province; established working groups on public investment to directly guide and remove difficulties and obstacles for investors with slow disbursement progress.

The province has notified the disbursement results to each Director of the Department, Branch, and Chairman of the District People's Committee every 10 days; at the same time, units that disburse below the average level of the whole province report the progress and implementation plan for the next 10 days every 10 days. Regularly review and transfer capital for projects with slow disbursement.

bna_IMG_5278.jpg
Director of the Department of Planning and Investment Pham Hong Quang presented a report on the implementation of the public investment plan for the first 9 months of 2023. Photo: Pham Bang

Director of the Department of Planning and Investment Pham Hong Quang said that as of September 20, the total public investment capital of Nghe An province had disbursed more than VND 4,979 billion, reaching 47.04% of the plan, of which the concentrated public investment source managed by the province had disbursed more than VND 2,982 billion, reaching 41.8% of the plan.

The whole province has 41 units disbursing above the provincial average, of which 30 units disbursed over 50%; 29 units were below the provincial average. After the provincial meeting, 18 units disbursed an increase of over 10%; 22 agencies and units had no change.

In particular, up to now, there are 10 units that have not yet disbursed, including: Department of Health, Vietnam - Germany College, Vinh Medical University, Provincial Employment Service Center, Department of Natural Resources and Environment, Yen Thanh District General Hospital, Nghe An Department of Standards and Quality Measurement, Provincial Border Guard Command, Department of Rural Development, Muong Qua High School.

bna_IMG_3234.jpg
Chairman of the Provincial People's Committee Nguyen Duc Trung inspected and urged the progress of the coastal road project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An). Photo: Pham Bang

Regarding the 2023 public investment plan, the National Target Program on New Rural Development reached 75.17%; the National Target Program on Sustainable Poverty Reduction reached 2.13%; the National Target Program on Ethnic Minority and Mountainous Areas reached 18.93%. The Socio-Economic Recovery and Development Program reached 18.41%.

By project, 80/160 projects have disbursed below the province's average, of which 34 projects have not yet disbursed. 5 projects under the Socio-Economic Recovery and Development Program have only disbursed 137,675 billion VND, reaching 18.41%. The Coastal Road Project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An) from Km7 - Km76 has disbursed 68.29%; Nghe An Oncology Hospital Project (phase 2) has disbursed 3.73%.

Director of the Department of Planning and Investment Pham Hong Quang said that, in addition to objective reasons, the subjective reason is that the management capacity of some investors is still limited, and some investors have not actively carried out payment procedures immediately after having volume.

thi-cong-ha-tang-ky-thuat-de-ngam-hoa-cap-vien-thong-dien-luc-tai-dai-lo-vinh-cua-lo-6777.jpeg
Contractor constructing technical infrastructure to bury telecommunications and electricity cables at Vinh - Cua Lo Boulevard project. Photo: Chau Lan

The professional capacity of some project management boards and consulting units... has not met the requirements, leading to slow completion of procedural documents. The survey and design work of some projects is not good and not thorough.

On the other hand, the Party committees and authorities in some localities have not been resolute in directing the disbursement of public investment capital and removing difficulties and obstacles. The working attitude and spirit of some officials working in public investment are not high, and the number of human resources is limited.


Source

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product