Implementing the North-South Expressway project and other key projects in Ha Tinh is a great determination of the entire Party and people. All levels, sectors and the entire political system are making every effort every day to resolve difficulties and obstacles, ensuring the set schedule. Therefore, all citizens must have a correct understanding of the law, and at the same time put national and community interests first and foremost.
With the democratic nature of the regime, the Vietnamese State always pays special attention to and puts the democratic freedoms of citizens first. The implementation of these rights must be based on the rule of law. However, in practice, in recent years, some citizens have taken advantage of democratic freedoms to infringe upon the interests of the State, the rights and legitimate interests of organizations and individuals and have been severely punished. This is a warning lesson for citizens who deliberately do not understand, or are gullible and listen to the instigation of bad people and outside forces, and disobey the provisions of the law. |
Thanks to the locality's good work in site clearance, the contractor has had an advantage in mobilizing machinery and equipment to construct the North-South expressway through Luu Vinh Son commune.
The project critical path cannot be changed.
According to the law, a project must go through many stages with strict procedures. Remember the case of building Vinh Hang Park in Bac Son commune in 2014, although the Provincial People's Committee at that time affirmed: "The implementation of the plan to build a cemetery park is an urgent requirement and has been carried out strictly, synchronously, ensuring procedures and regulations", but hundreds of people still gathered to protest, even attacked police officers, commune officials, and destroyed public property... The consequence was that the security and order situation in the area was complicated and prolonged, and some people had to serve prison sentences.
Currently, the Phuc Lac Vien - Hoan Vu Cremation Center project (in operation since 2017) is showing clear effects, showing its effectiveness in many aspects, especially in terms of civilization in burial, environmental protection, and contributing to saving the increasingly shrinking land fund.
The Phuc Lac Vien project (Luu Vinh Son commune, Thach Ha) increasingly affirms the practical significance, humanity, and correctness of the project's policy.
Many other similar cases also show that once an important project's critical path has been built and planned, it cannot be changed. Similar to the above project, the construction of the domestic solid waste treatment project in Huong Khe district has full scientific arguments and is very necessary, especially when the average annual amount of waste (period 2019-2033) in Huong Khe town and 8 communes (Gia Pho, Phu Phong, Huong Xuan, Huong Thuy, Huong Vinh, Phu Gia, Huong Long, Huong Binh) is about 7,535 tons (20.6 tons/day).
However, many local residents at that time had opposed and prevented the construction unit, complicating the situation. Up to now, after many years of implementation, the project has gradually been completed, people have realized the correctness of the project, helping to resolve the pressing issue of waste collection and treatment and implementing environmental criteria in building new rural areas...
Project of concentrated solid waste treatment area in Huong Khe district (Ha Tinh) seen from the outside.
In 2023, Ha Tinh determined to focus the highest on implementing the national key project of the North-South Expressway. This is a project identified by the Resolution of the 13th National Party Congress; the National Assembly and the Government prioritized resources for implementation. However, some people deliberately do not comply with the provisions of the law, thereby hindering the construction unit. The Party Committee and the government always respect and listen to the people, but on the basis of mutual respect for the law. President Ho Chi Minh also advised: "It is not what the people say, we just blindly follow" (1) .
Due to disagreement with the land compensation plan for the North-South Expressway project, some households in Khanh Vinh Yen commune (Can Loc) obstructed the construction unit. After applying many unsuccessful solutions (including receiving citizens, responding to petitions, direct dialogues...), on the afternoon of July 18, 2023, Can Loc District People's Committee coordinated with agencies, units and commune authorities to organize protection for the project construction through Chien Thang village.
Currently, in Can Loc as well as many other areas, the construction of the North-South Expressway is being implemented smoothly, ensuring progress.
Cua Dinh rice field area, Chien Thang village, Khanh Vinh Yen commune - where some people obstructed the construction of the North-South expressway project.
Mobilizing functional forces to protect the construction of a pontoon bridge across Ngan Mo River to serve the marking of the sand mine planning in My Yen village is also a solution that Cam Xuyen district is forced to implement. Because, to serve the North-South expressway project, the work must be carried out on schedule, according to plan, there is no other way.
Obstructing and affecting the progress of the North-South Expressway is also one of the reasons why Hoang Van Luan was prosecuted in 2023. Before being arrested in August 2023, among many acts Hoang Van Luan committed, was taking advantage of the construction of the North-South Expressway project to incite people to file complaints and hang banners in Hanoi with bad content.
Put yourself in a million hearts!
In 2023, in Luu Vinh Son commune (Thach Ha), there are 9 major projects that must conduct land acquisition, including important projects with large land acquisition areas such as: North-South expressway project (Ngo Quyen road project) with a total acquisition area of 6.7 hectares; North-South expressway project (Song Hanh road project, connecting DT.550 - Ham Nghi road) with a total acquisition area of 5.2 hectares; land clearance project for the North-South expressway project with a total acquisition area of 25.1 hectares; project to expand the Command Center, official housing, vocational training area for prisoners at Xuan Ha Prison with a total acquisition area of 13.4 hectares; commercial, service, tourism and sports area project in the Southwest of Thach Ha district with a total acquisition area of 79.76 hectares...
Mr. Tran Ba Hoanh - Chairman of the People's Committee of Luu Vinh Son commune said: "We have focused on the land acquisition and clearance work and the good news is that the people are very supportive of the policy, there is no situation where people oppose or obstruct the construction. Many people are very exemplary, even 2 families who are siblings have given up more than 32 hectares of forestry land that is producing quite well to serve the site of a key project, then moved to another place to receive forestry land even though production is not as favorable as before. Currently, the land acquisition work for major projects in the area is being carried out according to plan. Many households who relocated their houses to serve the North-South expressway project have come to build houses in the Cua Trua resettlement area, Vinh Cat village".
Many households have built new houses in Cua Trua Resettlement Area, Vinh Cat village, Luu Vinh Son commune, Thach Ha.
The reality of the land acquisition work in Luu Vinh Son commune as well as many other localities in Ha Tinh province shows that most people uphold the spirit of national interests and the interests of the entire people. Many households have proactively planned to relocate their houses and constructions, and have proactively carried out many tasks to hand over the land to serve important national and provincial projects for the common goal.
Although the community spirit of Ha Tinh people is typical, a small number of people still do not comply with the law, even obstructing the construction of key projects.
It is understandable that a part of the people of My Yen village (Cam My commune, Cam Xuyen) have concerns about the planning and exploitation of sand mines in the area. However, when the Party Committee and authorities from the province, district to local level promptly respond in many forms (organizing dialogues, propagating through articles in mainstream newspapers, television; through local radio channels, Facebook channels managed by departments, branches, localities; through meetings of associations, unions...), it is necessary to listen to have the right awareness, from there seriously implement.
The sand mining area in My Yen village from the red line to the bank of Ngan Mo river contributes to "straightening" the river flow, thereby improving the flood drainage capacity of Ke Go lake.
People in My Yen need to understand that, in order to implement the "critical path" of the key project directly directed by the Prime Minister, in addition to doing a good job of site clearance, the important thing is to exploit a large amount of soil and sand materials to serve the construction.
Therefore, the Provincial People's Committee has approved the exploitation of 11 new mines (8 landfill mines, 3 river sand mines) to serve the construction of the North-South expressway through Ha Tinh. Among these, there is a sand mine in My Yen village.
On December 12, 2023, some Facebook accounts posted false information about the My Yen sand mining plan.
“The My Yen sand mine planning area has a total area of 3.48 hectares; of which more than 1.7 hectares are managed by the Commune People's Committee, river land, fallow land, alluvial land; the rest has been allocated to the people. This planning area has an area related to 86 households directly engaged in production. The land plots here are quite small and fragmented. This land has low production efficiency and is often abandoned.
We are focusing on resolving each part of the work related to site clearance and are confident that the people will agree and contribute with the whole province to ensure the progress of the national key project according to the drastic and close direction of the Government, ministries, branches and the province", Mr. Ha Huy Hung - Chairman of Cam My Commune People's Committee expressed.
Continue to implement many key projects
In 2024, Ha Tinh identified it as a breakthrough year to complete the 5-year plan 2021-2025. At the meeting at the end of 2023, the Provincial People's Council determined that in 2024, it will continue to mobilize and effectively use all resources, build synchronous socio-economic infrastructure, attract and accelerate key projects.
From there, the Resolution of the Provincial People's Council affirmed: continue to coordinate with the Ministry of Transport to deploy and promote investment in key transport projects (North-South expressway, Vung Ang - Tan Ap - Mu Gia railway, upgrading and expanding National Highway 12C...); strengthen support activities, attract investment in fields, areas, projects according to the orientation of the Provincial Planning, especially large projects, strategic investors, wishing to invest in Ha Tinh (VFT, Vingroup, Sun Group, FPT, Ecopark, Silk Path, T&T, PV Gas...).
The nearly 1,600 billion VND project invested by VSIP will be built on an area of over 190 hectares located in Bac Thach Ha Industrial Park (In photo: The project exploitation area is not far from the North-South Expressway).
The volume of national key projects and important projects of the province involving many large and potential investors will be accompanied by very strict requirements on site clearance. Therefore, at the closing session of the 17th Session of the 18th Provincial People's Council, Comrade Hoang Trung Dung - Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council emphasized: It is necessary to strengthen support activities, attract investment; coordinate and create conditions for enterprises to implement committed projects; focus on removing difficulties and obstacles for key projects; soon start the VSIP Industrial Park Infrastructure Project, investment projects in infrastructure of industrial parks/clusters, urban areas, tourism.
Vung Ang Economic Zone with the core being the Formosa steel factory and the deep-water port cluster of Vung Ang - Son Duong is identified as the growth driving force of the province.
We firmly believe that, with the great efforts and determination of all levels, sectors and the entire political system, the implementation of key projects in Ha Tinh will proceed smoothly and receive high consensus from the people.
We believe that many people in Ha Tinh will also understand more clearly the strictness of the law to live consciously, understand and always "respect the law", at the same time firmly consolidate the traditional cultural values and people of Ha Tinh: patriotism is associated with consensus and dedication; patriotism, Ha Tinh people are ready to "leave no regrets for the house if the car has not passed"!
----------
1. Hoang Viet, Do not confuse the democratic method with “following the masses” , Communist Magazine, October 2023 issue, p.97.
Manh Ha - Vu Vien