Hundreds of workers work day and night on the main bridge of Rach Mieu 2 Bridge - Photo: MAU TRUONG
On March 28, Mr. Tran Van Thi - Director of My Thuan Project Management Board (Ministry of Construction) - said that he responded to the emulation movement and achieved the achievement of "45 days and nights to speed up the construction progress of the Rach Mieu 2 Bridge investment project".
Currently, all 500 workers and nearly 100 technical staff are working day and night, stretching 17km across the entire Rach Mieu 2 Bridge construction project.
"All for the goal of bringing the Rach Mieu 2 bridge project to completion on April 30 on the occasion of the 50th anniversary of the complete liberation of the South and national reunification, by the end of June completing the access roads on both sides of Tien Giang and Ben Tre provinces, completing the project and putting it into use on September 2, 2025," Mr. Thi added.
According to Mr. Thi, the overall progress of the project is currently more than 82% complete, 4.5% ahead of schedule.
As for the main bridge, Rach Mieu 2 Bridge has installed the 104th/112th cable-stayed cable bundle, about 15% ahead of schedule.
The Rach Mieu 2 Bridge project starts at Dong Tam intersection (Chau Thanh district, Tien Giang province), and ends at National Highway 60, about 700m from the northern abutment of Ham Luong bridge (Ben Tre city, Ben Tre province).
Rach Mieu 2 Bridge across the Tien River, connecting the two provinces of Tien Giang - Ben Tre, started construction at the end of March 2022 with a total investment of 6,810 billion VND, using state budget capital.
The construction of Rach Mieu 2 Bridge is intended to "share the burden" of the existing Rach Mieu Bridge, which is currently overloaded and often has traffic jams.
Rach Mieu 2 Bridge crosses the Tien River, located about 4km upstream of Rach Mieu 1 Bridge on the Tien River - Photo: MAU TRUONG
Workers are constructing the main bridge of Rach Mieu 2 Bridge - Photo: MAU TRUONG
Workers work at a height of dozens of meters above the Tien River under the scorching sun - Photo: MAU TRUONG
The road leading to Rach Mieu 2 Bridge, Tien Giang province side, is also being accelerated - Photo: MAU TRUONG
The main bridge section of Rach Mieu 2 Bridge has installed the 104th/112th cable-stayed cable bundle, about 15% ahead of schedule - Photo: MAU TRUONG
The distance between the two sides of Rach Mieu Bridge is about 20m, Rach Mieu 2 Bridge is expected to be closed on April 30 - Photo: MAU TRUONG
Workers are constructing the approach road to Rach Mieu 2 Bridge - Photo: MAU TRUONG
Rach Mieu 2 Bridge is expected to be completed and put into use on September 2, 2025 - Photo: MAU TRUONG