According to the decision, the route length is about 98.35km. The route follows the Cam Lo - La Son expressway currently in operation.
The starting point (Cam Lo) is at Km 0+000, connecting to the end point of the Van Ninh - Cam Lo expressway project in Cam Hieu commune, Cam Lo district, Quang Tri province. The end point (La Son) is at about Km 102+200, connecting to the starting point of the La Son - Hoa Lien project in Loc Bon commune, Phu Loc district, Thua Thien Hue province.
The Cam Lo - La Son route is 98.3km long, of which 37.3km passes through Quang Tri province and 61km passes through Thua Thien - Hue (Photo: internet).
Investment in expanding the roadbed, road surface and works on the route from two lanes to four lanes. This is a group A project, invested in the form of public investment.
The total investment of the project is nearly 6.5 trillion VND from the state budget. Of which, the general reserve capital of the medium-term public investment plan from the central budget for the period 2021-2025 corresponding to the increased central budget revenue in 2023 approved by the National Assembly in Resolution No. 142/2024/QH15 dated June 29, 2024 is 5,488 billion VND. The capital source of the medium-term public investment plan for the period 2026-2030 is 1,000 billion VND.
The project's governing body is the Ministry of Transport.
The People's Committees of Quang Tri and Thua Thien Hue provinces are responsible for organizing and implementing site clearance, resettlement, and land use conversion (if any).
At the same time, the People's Committees of Quang Tri and Thua Thien Hue provinces coordinate with the Ministry of Natural Resources and Environment, the Ministry of Transport and relevant ministries and branches on the exploitation of common material mines in the area according to planning, in accordance with legal regulations, meeting the project's progress...
Source: https://www.baogiaothong.vn/duyet-dau-tu-gan-65-nghin-ty-dong-mo-rong-cao-toc-cam-lo-la-son-192241023164349164.htm