Ho Chi Minh City and Tay Ninh province will set up 3,029 boundary markers to serve compensation, support, and resettlement work to implement the Ho Chi Minh City - Moc Bai expressway project.
Planting more than 3,000 landmarks in complex, swampy terrain to construct the billion-dollar Ho Chi Minh City - Moc Bai expressway
Sunday, March 9, 2025 12:18 PM (GMT+7)
Ho Chi Minh City and Tay Ninh province will set up 3,029 boundary markers to serve compensation, support, and resettlement work to implement the Ho Chi Minh City - Moc Bai expressway project.
The Ho Chi Minh City - Moc Bai Expressway is 51 km long, starting from Ho Chi Minh City Ring Road 3 (Cu Chi District) and ending at National Highway 22 in Ben Cau District, Tay Ninh Province. This is a particularly important project, meeting transportation needs, reducing traffic congestion and ensuring traffic safety; developing the industrial - urban chain Moc Bai - Ho Chi Minh City - Cai Mep - Thi Vai Port; promoting socio-economic development of Ho Chi Minh City, Tay Ninh and the provinces in the Southeast region. (Perspective image).
In preparation for the project implementation, from February 2025 to present, Ho Chi Minh City and Tay Ninh province have been focusing on marking and demarcating boundaries to serve the work of compensation, support and resettlement.
According to Dan Viet reporter, in Nhuan Duc commune, Cu Chi district, the group planting stakes and determining boundaries to serve the work of boundary crossing and compensation for site clearance for the project is actively working.
After measuring and determining the boundary, the clearance markers will be fixed 100 meters apart. Because the highway passes through many complex terrains, swamps, dense trees... the marker planting team had to work quite hard.
A representative of the People's Committee of Nhuan Duc Commune, Cu Chi District, said that there are 291 cases in the commune affected by the Ho Chi Minh City - Moc Bai Expressway project, of which 10 cases are public land. The locality has conducted a preliminary inventory and coordinated with the investor, the team planted markers to determine the boundary location to implement the project. Up to now, the people have grasped the project information, accompanied and are ready to hand over the site to the investor in the near future.
The entire route has 3,029 milestones, Ho Chi Minh City and Tay Ninh province will complete in March 2025 to do the next work.
In Ho Chi Minh City alone, the Ho Chi Minh City - Moc Bai expressway project is 24.7 km long. From February 2025 to March 15, Ho Chi Minh City will install 1,083 markers; from March 15 to March 31, 126 markers will be installed. In parallel with Ho Chi Minh City, Tay Ninh province is also doing similar work. In addition to installing markers, units will also conduct mine clearance in Ho Chi Minh City and Tay Ninh province, scheduled for April 25.
The Ho Chi Minh City - Moc Bai Expressway (phase 1) was approved by the Prime Minister for investment under the public-private partnership (BOT contract) method with an investment including interest of VND 19,617 billion, implementation period from 2024 to 2027. (Perspective photo).
Ho Chi Minh City - Moc Bai Expressway has a scale of 6 lanes, in phase 1 the project invests in 4 standard lanes and 2 continuous emergency lanes. Land clearance is carried out at one time according to the scale of 6 lanes on the entire route. (Perspective image).
It is expected that Ho Chi Minh City and Tay Ninh will complete the counting and measuring work before April 30, 2025, approve the resettlement compensation project before June 30, 2025, start construction of component project 2 "Investment in construction of residential roads and overpasses across the highway" (construction packages using budget capital) on September 2, 2025 and start construction of component project 1 "Investment in construction of Ho Chi Minh City - Moc Bai highway (phase 1)" in January 2026.
Dieu Binh