Nam Ly Bridge (replacing Rach Chiec Dam) is one of the key projects in Thu Duc City (HCMC). The project has special significance in connecting traffic infrastructure, creating space and driving force for socio-economic development in the area.

W-DJI_0973.JPG.jpg
The Nam Ly Bridge construction project to replace Rach Chiec dam has reached 90% of the work volume. Photo: TK

The Nam Ly Bridge project has a total length of 750m, of which the bridge is 450m long, 20m wide, and the approach road is 30 - 37m wide. The total investment is 919 billion VND, including construction costs of 423 billion VND, compensation for site clearance of 403 billion VND for 51 households and 3 affected organizations...

After 3 years of construction and reaching about 40% of the contract value, the project was temporarily suspended in early 2019 due to land acquisition problems. It was not until March 25, 2023, after 4 years of "shelving", that the project officially resumed construction.

W-DJI_0961.JPG.jpg
The project's total investment has been reduced from VND919 billion to about VND731 billion. Photo: TK

According to the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City (investor), after nearly 1.5 years of restarting, the overall progress of the project has reached about 90%.

The project is expected to open to traffic in mid-September. After that, contractors will close the existing side road to construct a residential access road and auxiliary items.

Currently, the consortium of contractors is mobilizing 60 workers and more than 10 specialized machines to complete the items, aiming to complete the entire project by the end of this year.

dsc7595jpg 355.jpg
When completed, Nam Ly Bridge will replace the narrow and degraded Rach Chiec dam bridge, remove the "bottleneck" on Do Xuan Hop Street, and contribute to completing the traffic network in the East of Ho Chi Minh City.
W-_DSC7520.JPG.jpg
Workers are installing the railing system and electrical infrastructure of Nam Ly bridge. Photo: TK

According to the latest update from the investor, the Nam Ly bridge project's cost has been reduced from 919 billion to more than 731 billion VND.

The total investment in the project decreased because previously, at the stage of establishing a new project, the units only estimated the compensation price and the land origin was all residential land.

However, when compensation was officially implemented and the land origin was accurately determined, the proportion of agricultural land increased. Therefore, compensation costs decreased, so the total investment decreased as above.

500 billion VND bridge connecting two districts in Ho Chi Minh City will soon help people avoid the 10km detour

500 billion VND bridge connecting two districts in Ho Chi Minh City will soon help people avoid the 10km detour

Rach Cay Kho Bridge connecting Nha Be district with Binh Chanh, Ho Chi Minh City is expected to open to traffic in early September, helping people move conveniently, avoiding the situation of "crossing the river by ferry" or going in a 10km detour.
Two 1,500 billion VND bridges to ease traffic congestion in the East of Ho Chi Minh City are about to be completed

Two 1,500 billion VND bridges to ease traffic congestion in the East of Ho Chi Minh City are about to be completed

At the construction sites of the two Nam Ly and Tang Long bridge projects (Thu Duc City, Ho Chi Minh City), contractors are making efforts to carry out synchronous construction and speed up the completion progress in the last months of this year.
Closing of 919 billion VND bridge at the gateway to Ho Chi Minh City after 6 months of reconstruction

Closing of 919 billion VND bridge at the gateway to Ho Chi Minh City after 6 months of reconstruction

After 6 months of construction resuming after 4 years of being "shelved" due to land acquisition issues, the Nam Ly bridge project with a total investment of 919 billion VND has officially closed the first bridge branch.