Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City focuses on implementing the project to build 4,500 classrooms

NDO - On April 1, the Supervisory Delegation of the Culture and Society Committee of the Ho Chi Minh City People's Council had a working session with the Department of Finance, the Department of Education and Training, and the Management Board of Investment Projects for Construction of Civil and Industrial Works of Ho Chi Minh City on the implementation of the Project to build 4,500 classrooms to celebrate the 50th anniversary of the Liberation of the South and National Reunification Day.

Báo Nhân dânBáo Nhân dân01/04/2025

Reporting to the monitoring delegation, a representative of the Ho Chi Minh City Department of Education and Training said that after one year of implementing the project, the progress of the project to build 4,500 classrooms was slower than planned, the number of completed classrooms put into use did not reach the set target but showed the determination and efforts of departments, branches, sectors and localities.

In the 2021-2025 period, the education sector has been allocated about VND 18,288 billion, accounting for more than 10% of the total public investment capital of Ho Chi Minh City to invest in increasing classrooms, promptly meeting the mechanical population growth rate, ensuring school places for students.

It is expected that by the end of this year, 2,000 new classrooms will be put into use, including 1,200 classrooms from public investment and 800 classrooms from socialization, reaching 50% of the set target.

Ho Chi Minh City focuses on implementing the project to build 4,500 classrooms photo 1

Ho Chi Minh City students take the 10th grade entrance exam.

The reason for the slow implementation progress is that the 2021-2025 medium-term public investment period has changes in planning, land, environmental conditions, traffic, etc.

Many new school construction investment projects are planned on land that requires site clearance, compensation, and multi-step implementation processes, fluctuating prices, etc., leading to increased demand for investment capital.

Regarding investment in the education sector under the public-private partnership model, this is a new form of investment, regulations and guidelines are not specific, so there are still many difficulties in attracting domestic and foreign investors.

From the above problems, the Department of Education and Training of Ho Chi Minh City recommends that competent authorities quickly resolve procedures for establishing, synthesizing, submitting for appraisal and approval of planning adjustment projects.

At the same time, assign the Department of Finance and the Department of Natural Resources and Environment to coordinate with localities to review and develop plans to increase land funds for education.

Resolutely handle the responsibility of investors who have been assigned land by the city and approved investment policies in new residential areas but have not yet fulfilled their obligations to invest in schools according to planning and commitments...

Along with that, promote the policy of socializing education in the direction of allowing investors to use land that is not included in the education planning and is not subject to land use purpose change according to the provisions of Clause 1, Article 121 of the 2024 Land Law to build private schools with educational operation duration according to the lease term (minimum 5 years)...

Ho Chi Minh City focuses on implementing the project to build 4,500 classrooms photo 3
Mr. Cao Thanh Binh, Head of the Culture and Social Committee of Ho Chi Minh City People's Council spoke at the supervision session.

At the monitoring session, Mr. Cao Thanh Binh, Head of the Culture and Social Committee of the Ho Chi Minh City People's Council, highly appreciated the efforts of relevant units in implementing the construction of schools and classrooms.

At the same time, it is recommended that relevant departments and branches focus on finding solutions to remove obstacles and effectively implement the Project to build 4,500 classrooms.

For projects that have not yet approved investment policies, the Department of Education and Training will promptly consult with city leaders to have new investment policies to keep up with implementation progress.

Source: https://nhandan.vn/thanh-pho-ho-chi-minh-tap-trung-trien-khai-de-an-xay-dung-4500-phong-hoc-post869329.html


Comment (0)

No data
No data

Same category

Son Doong Cave is among the top 'surreal' destinations like on another planet
Wind power field in Ninh Thuan: Check-in "coordinates" for summer hearts
Legend of Father Elephant Rock and Mother Elephant Rock in Dak Lak
View of Nha Trang beach city from above

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product