02/17/2024 15:07
(Baohatinh.vn) - The 500kV line 3, Quang Trach - Quynh Luu, section through Ha Tinh, is over 141 km long. The project started on January 18, 2024. Currently, contractors are simultaneously constructing 93/285 handed-over foundation locations.