Da Nang: Rocks and soil from Cam Le industrial park continuously flooded into houses during heavy rains, damaging the property of many households.

On November 16, many households in Group 5, Hoa Tho Tay Ward, Cam Le District, had not yet removed the sandbags across the gate and the 40cm high brick wall surrounding the porch to prevent rocks and soil from entering the house.

While the consequences of the flood a month ago have not yet been resolved, in recent days, people have continued to suffer from rocks and mud from the Cam Le industrial cluster. "Whenever it rains heavily, it floods. People have to stay up all night to watch for water from the industrial cluster," said Mr. Tran Viet Phuc, 48 years old.

His wife works as a factory worker, and his children are fed up with the situation of "running away every time it rains and flooding" so they go to stay at a friend's house. Mr. Phuc had to quit his job to take care of the house. The family's three rice jars on the porch are moldy, and many of their belongings in the house have been damaged after the recent floods.

On the opposite side, the family of Mr. Tran Viet Mat, 60 years old, had four jars of rice damaged, along with a television, refrigerator, and washing machine. A few days ago, his daughter's laptop, which she had just bought for over 20 million VND and was left on a chair, was also damaged by floodwaters that flooded into the house, reaching nearly half a meter deep.

Mr. Tran Viet Phuc's family had to use sandbags, planks to block the gate, and build a brick wall in front of the porch, but still could not prevent mud from the Cam Le industrial cluster from flooding in every time it rained heavily. Photo: Nguyen Dong

Mr. Phuc used sandbags and planks to block the gate and built a brick wall in front of the porch, but still could not prevent mud from flooding into the house every time it rained heavily. Photo: Nguyen Dong

During the flood in mid-October, households said that each family was supported with a box of instant noodles and 10 kg of rice. The People's Committee of Cam Le District, the investor of the industrial park project, later informed that 16 households were affected by mud from the industrial park flowing into their homes. The district and the contractor are calculating the support costs and will not use the budget. However, a month has passed and the people have not received any support or compensation.

The district explained that the reason why mud and soil flowed down to people's houses was because the embankment was newly completed, the ground structure was not stable, while the rainfall was sudden and the drainage infrastructure outside the industrial park was not completed.

Regarding measures to deal with mud and soil from the project flowing into people's houses, the District People's Committee said it will build a drainage system for residential areas, reinforce the slope with a reinforced concrete frame, combine planting trees to isolate residential areas and plant grass to reduce erosion.

The drainage system for the industrial park adjacent to residential areas has been invested in, but construction is still unfinished. Photo: Nguyen Dong

The drainage system for the industrial park adjacent to residential areas is under construction. Photo: Nguyen Dong

However, on November 15, the project was reported to be empty of workers despite the clear weather. The drainage system is under construction for a 5-meter section, with many items yet to be implemented.

"If there is construction, there will only be a few workers, and we don't know when it will be finished," said Mr. Tran Viet Phuc, worried that he will have to live with mud flooding into his house because heavy rain is forecast to last for many more days.

Cam Le Industrial Cluster Technical Infrastructure Project is on the list of key projects, approved by Da Nang City People's Council in December 2019, with a planning area of ​​over 29 hectares and a total investment of 250 billion VND.

Up to now, the basic items have been completed but the project has not connected the western infrastructure with Nguyen Phu Huong Street according to the plan, leading to the industrial park having no entrance.

The drainage from residential area group 5 to Cau Do river is also not completed. Photo: Nguyen Dong

The drainage system from the residential area to the Cau Do River is not yet completed. Photo: Nguyen Dong

The Cam Le industrial cluster project was criticized by Da Nang Party Secretary Nguyen Van Quang during a site inspection in September, because the trees used to prevent erosion were eucalyptus saplings, only as tall as an adult's knee.

Mr. Quang also commented that the project's slope is dangerous, requiring the investor, consulting unit and Department of Construction to study and find suitable solutions to ensure safety for both the industrial park and surrounding residential areas.