Current status of key projects in Dak Nong

Many key projects and works of Dak Nong are actively being implemented, speeding up progress, and completing soon.

Báo Đắk NôngBáo Đắk Nông28/03/2025

Dak Nong identified the Gia Nghia - Chon Thanh Expressway Project as a key project of the province. Dak Nong provincial leaders (in the photo is Comrade Ngo Thanh Danh, Secretary of the Provincial Party Committee, Head of the Provincial National Assembly Delegation (wearing a hat) with the working delegation) regularly inspected and directed strongly to start construction of the expressway before April 30, 2025.
Dak Nong has identified the Gia Nghia - Chon Thanh Expressway Project as a key project of the province and plans to start construction before April 30, 2025. (Photo: Comrade Ngo Thanh Danh, Secretary of the Provincial Party Committee, Head of the Provincial National Assembly Delegation, inspected the progress of the expressway project in February 2025)
a1 352A1238
The Dak Nong Provincial Museum, Library and Park Complex project has a total investment of more than 124 billion VND. The project has completed about 50% of the volume and the construction has encountered many difficulties due to the land acquisition of 0.54ha of 12 households (Photo: a corner of the building of the project under construction due to land acquisition)
a2 352A1136
The project to relocate and resettle 212 households in the central area of ​​Gia Nghia City requires the recovery of 9.72 hectares of 120 cases in Nghia Duc, Nghia Trung and Nghia Thanh wards. The land clearance has been very slow in the past (Photo: Houses in the area of ​​land recovery in Nghia Duc ward) and currently Gia Nghia City has not completed the documents to approve specific land prices.
a3 DJI_0279
Gia Nghia Central Square project has now completed about 62% of the contract value. In which, the exhibition center project has basically completed the construction part.
a4 352A1134
The Gia Nghia Central Square yard is still short of 140,000m3 of land to be leveled with the central building. From the current ground, it is necessary to raise about 10m to reach the square yard which has been basically completed.
a5 352A1285
The Dao Nghia - Quang Khe road project (phase 2) passes through Gia Nghia city, is more than 18km long, affecting about 358 households on an area of ​​about 71ha. Currently, the government has mobilized people to proactively hand over about 2km and started construction right in this area.
a6 DJI_0311
The Dak Nong General Hospital Upgrade Project has a total investment of 753 billion VND and is now over 50% complete. The project is in the acceleration phase with the goal of completion before September 30, 2025.
a7-352a1361-7540bc933bc29f159871ea09ec88b72e.jpg
Night shift construction workers at the Provincial General Hospital Upgrade Project

Source: https://baodaknong.vn/hien-trang-nhung-cong-trinh-trong-diem-cua-dak-nong-247566.html