Termination of contract with contractor violating progress

Báo Giao thôngBáo Giao thông24/12/2024

The Traffic Department officially terminated the contract with the contractor Anh Vinh Group Joint Stock Company due to serious violations of the construction progress according to the contract.


On December 24, information from the Traffic Construction Investment Project Management Board (Traffic Board) said that the unit officially decided to terminate contract 378/2018/HDTC-KQLĐTND-AV dated March 16, 2018 with Anh Vinh Group Joint Stock Company.

Dự án chống sạt lở bán đảo Thanh Đa: Chấm dứt hợp đồng với nhà thầu vi phạm tiến độ- Ảnh 1.

Thanh Da peninsula landslide prevention project is sluggish after many years of construction.

This is a contract to implement the construction package of the above-ground part (embankment body and embankment top) of the Thanh Da Peninsula Erosion Prevention Project - Section 2 (Saigon River - Saigon Domaine Hotel Area) and related contract appendices.

The reason given by the Traffic Department is that Anh Vinh Group Joint Stock Company did not fulfill its obligations to extend the contract guarantee and advance payment guarantee; seriously violated the construction progress according to the contract as well as the commitments with the Traffic Department in meetings, seriously affecting the progress, quality and efficiency of the bid package; abandoned the project, exceeding the deadline by 56 consecutive days without performing the work according to the contract.

The Traffic Department assigns the Waterway Project Management Board to preside over and be responsible for drafting the report, submitting the contract termination to the competent authority and the termination procedures according to regulations.

At the same time, work with relevant units to determine the financial obligations and other obligations of contractor Anh Vinh when terminating the contract; determine the remaining workload, and organize implementation in accordance with current regulations.

The Thanh Da Peninsula landslide prevention project - section 2 has a total length of 2.797km with an investment capital of over 319 billion VND from the city budget. The above-ground construction package (embankment body and embankment crest) is implemented by the joint venture of Anh Vinh Group Joint Stock Company - Thanh Hung Company Limited - Vu Bach Trading and Construction Company Limited, starting construction in 2018.

Regarding the progress of implementation, Thanh Hung Company Limited and Vu Bach Trading and Construction Company Limited have completed 98% of the work volume according to the joint venture agreement. Anh Vinh Group Joint Stock Company has only completed 18% of the work volume and has stopped construction, failing to meet the progress.

TP.HCM: Đánh thức bán đảo Bình Quới - Thanh Đa Ho Chi Minh City: Awakening the Binh Quoi - Thanh Da peninsula

After 32 years of suspended planning, the future of Thanh Da - Binh Quoi peninsula (Binh Thanh district, Ho Chi Minh City) is being re-drafted through a planning design competition, as a basis for restarting investment projects in this area.



Source: https://www.baogiaothong.vn/du-an-chong-sat-lo-ban-dao-thanh-da-cham-dut-hop-dong-voi-nha-thau-vi-pham-tien-do-192241224143836914.htm

Comment (0)

No data
No data

Same tag

Same category

Victory - Bond in Vietnam: When top music blends with natural wonders of the world
Fighter planes and 13,000 soldiers train for the first time for the April 30th celebration
U90 veteran causes a stir among young people when he shares his war story on TikTok
Moments and events: April 11, 1975 - The battle in Xuan Loc was fierce.

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product