Vietnam.vn - Nền tảng quảng bá Việt Nam

Close-up of the 500kV line through Ha Tinh gradually completed

Việt NamViệt Nam01/07/2024


TPO – Of the 285 electric poles across Ha Tinh, many locations have gradually completed the cable pulling. Meanwhile, some other electric poles in difficult and rugged terrain are being erected by contractors, completing them soon as planned.

Close-up of the 500kV line through Ha Tinh. Video: Pham Truong

Close-up of the 500kV line through Ha Tinh, gradually completed, photo 1

In early July, although the 500kV line 3 Quang Trach - Pho Noi project could not be energized on June 30 as the target set by the Prime Minister, thousands of officials, engineers and workers in the electricity industry along the line are working hard to complete the project soon.

Close-up of the 500kV line through Ha Tinh, gradually completed, photo 2

The 500kV line 3 project through Ha Tinh is over 141km long with 285 pole foundation locations, 284 pole spaces/113 anchor spaces in 9 districts and towns. This is the locality assessed to have the largest workload and the most difficult terrain among the provinces where the line passes. After many months of construction, up to now, many locations on the line are gradually being completed.

Close-up of the 500kV line through Ha Tinh, gradually completed, photo 3

According to the design, each electric pole will have 26 wires (24 electric cables, 1 optical cable, 1 lightning protection wire).

Close-up of the 500kV line through Ha Tinh gradually completed photo 4

Despite the heat, groups of workers still stayed to work, completing the line early. In the picture is the pole position across Hoa Lac commune (Duc Tho district, Ha Tinh), workers are completing the final stage of pulling the wire.

Close-up of the 500kV line through Ha Tinh gradually completed photo 5

Meanwhile, in some locations with difficult terrain, high mountains, rivers and lakes, due to difficulties in transporting materials and equipment, the erection of poles is being urgently completed.

Close-up of the 500kV line through Ha Tinh, gradually completed, photo 6
Close-up of the 500kV line through Ha Tinh gradually completed photo 7

The position of column 175 across Boc Nguyen lake (Cam Thach commune, Cam Xuyen district) is gradually being completed to move to the wire pulling stage.

Close-up of the 500kV line through Ha Tinh gradually completed photo 8

According to engineers from Song Da Construction and Service Joint Stock Company, this is one of the three tallest support columns on the line with a height of 145m, weighing 426 tons, using pipe column coupling technology, the first time used in a super high voltage power line project in Vietnam. The contractor spent a lot of time erecting these columns.

Close-up of the 500kV line through Ha Tinh gradually completed photo 9

At the pillars over houses and irrigation canals of Ke Go lake through Cam My commune (Cam Xuyen district), the contractor had to set up scaffolding as a support to pull the wire.

Close-up of the 500kV line through Ha Tinh gradually completed photo 10

Mr. Luong Thanh Trung (PC01 Joint Stock Company, Hanoi) said that each coil of power line wire is 2,000-2,400m long and weighs 5-6 tons. To spread and hang the wire, in addition to human power, plows and line winches are also needed.

Close-up of the 500kV line through Ha Tinh gradually completed photo 11

“The wire laying process requires crossing forests, mountains, lakes, and canals, so it is very difficult. In difficult locations, we have to use supports, lift the wire, and pull the cable along the lead wire to avoid crossing the wire,” said Mr. Trung. In the photo, workers carefully tie each scaffolding to ensure safety when pulling the wire.

Close-up of the 500kV line through Ha Tinh gradually completed photo 13

Groups of workers worked through lunch to ensure the goal of pulling the electricity early.

Close-up of the 500kV line through Ha Tinh gradually completed photo 14
Close-up of the 500kV line through Ha Tinh gradually completed photo 15

The representative of the Central Power Project Management Board (CPMB - investor of the 500 kV line 3-circuit project, Quang Trach - Quynh Luu section) said that up to now, 160 poles have been erected, 125 poles are being erected; 15/113 anchorages have been wired. Currently, contractors are speeding up the progress to soon complete the line locations.

Image of the giant transformer station of the 500kV circuit 3 project in Pho Noi, Hung Yen reaching the finish line ahead of schedule

Image of the giant transformer station of the 500kV circuit 3 project in Pho Noi, Hung Yen reaching the finish line ahead of schedule

Proudly, the Union flag flutters on the 500kV power pole, circuit 3, section through Nghe An.

Proudly, the Union flag flutters on the 500kV power pole, circuit 3, section through Nghe An.

Beautiful images of green shirt volunteers contributing to the 500kV line 3 project

Beautiful images of green shirt volunteers contributing to the 500kV line 3 project

Pham Truong


Comment (0)

No data
No data

Same tag

Same category

Young people "revive" historical images
Close-up of the soldiers' hard training hours before the April 30th celebration
Ho Chi Minh City: Coffee shops decorated with flags and flowers to celebrate the 30/4 holiday
36 military and police units practice for April 30th parade

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product