
Low disbursement rate
According to the report, the total investment capital in 2024 of Tien Phuoc district is 236.5 billion VND; by August 30, the disbursement reached 98 billion VND (41.4% of the plan).
Currently, there are many public investment projects in Tien Phuoc district. The Cay Coc Struggle Memorial Project (Tien Tho commune) has a total investment of 30 billion VND, the implementation period is 2021 - 2023 but due to slow progress, the Provincial People's Committee has extended the project until the end of 2024.
Tien Phuoc District People's Committee has developed a plan to compensate, support and resettle 5 households whose land and houses have been affected. Up to now, many households have received compensation but have not yet agreed on resettlement locations.
Mr. Tram Que Huong - Chairman of Tien Phuoc District People's Committee committed to completing the central stele house by September 30 and the reception house by December 31.
From now until the end of the year, it is expected that an additional 2 billion VND will be disbursed. The remaining capital is proposed to be extended to 2025 by the Provincial People's Committee or transferred to another project with payment volume.
In addition, the project to promote the value of the Huynh Thuc Khang Memorial House (Tien Canh commune) is also behind schedule. Tien Phuoc District People's Committee committed to completing site clearance by December 31, 2024 and completing the project by March 20, 2025.
Mr. Tram Que Huong said that the disbursement of public investment capital by August 30, at 41.4%, was lower than planned. The reason was that investment procedures for some projects were slow, leading to slow disbursement.
The work of land acquisition and clearance is stuck but has not been resolved in time. The work of managing the current status, agreeing on compensation prices for land acquisition and clearance, and confirming the origin of land use still has many problems.
Contractors have lost financial capacity, leading to many projects being behind schedule. The progress of projects under the new rural criteria at the district level is still slow, and many transitional projects still have no disbursement volume...

Speed up disbursement
Mr. Pham Van Doc - Secretary of Tien Phuoc District Party Committee requested the district's agencies and departments to shorten the time for reviewing project documents and procedures as much as possible.
Investors must review projects with low disbursement rates and focus on settlement as soon as there is work volume. Communes and towns must step up propaganda and mobilize people to agree on site clearance.
For completed projects and works put into use, promptly prepare documents and procedures to submit to the settlement audit agency according to regulations.
Investors focus on checking and proposing projects that are not able to disburse funds to switch to projects that are able to disburse funds. "The entire district has raised the responsibility of leaders to speed up the disbursement of capital plans for projects," said Mr. Doc.
Mr. Tram Que Huong said that Tien Phuoc has currently focused on mobilizing and integrating many capital sources to implement programs and projects, especially focusing on speeding up the progress of implementing projects to build new rural districts.
Tien Phuoc still has many urgent projects that need investment but resources have not been balanced. In addition, through review, the district's basic construction debt is still very large, while the district's budget resources are limited, the progress of land exploitation is slow, and mobilizing non-budgetary resources is difficult.
The District People's Committee proposed that the Provincial People's Committee consider and support the district with a part of the budget to pay debts, pay off the volume, speed up the progress of projects that have been settled, have large debts and urgent projects that need investment of about 76 billion VND.
Vice Chairman of the Provincial People's Committee Tran Nam Hung agreed with the plans and solutions to accelerate public investment disbursement of Tien Phuoc district and requested the Tien Phuoc district People's Committee to make a commitment to send to the Provincial People's Committee for monitoring, urging, and directing the resolution of arising problems. Assign comrades in the Standing Committee of the District Party Committee to inspect the progress of projects weekly and hold meetings to provide appropriate instructions.
“The entire political system of Tien Phuoc district must take more drastic and urgent measures to accelerate public investment disbursement. By December 31, Tien Phuoc needs to disburse 100% of capital to implement target programs, transferred capital and 2023 capital, which can be extended to 2024,” emphasized Vice Chairman of the Provincial People's Committee Tran Nam Hung.
Source: https://baoquangnam.vn/tien-phuoc-thuc-day-giai-ngan-von-dau-tu-cong-3140823.html
Comment (0)