Actively remove difficulties and promote progress of key energy projects and works

Báo Tài nguyên Môi trườngBáo Tài nguyên Môi trường23/08/2024


Tích cực gỡ khó, thúc đẩy tiến độ các công trình, dự án năng lượng trọng điểm- Ảnh 1.
Deputy Prime Minister Tran Hong Ha highly appreciated the commitment of localities to complete site clearance and hand over to investors to carry out items and works related to Nhon Trach 3 and 4 thermal power projects and the power grid to release capacity... - Photo: VGP/Minh Khoi

According to the report of the Ministry of Industry and Trade, up to now, the Ministry has worked with Vietnam Electricity Group (EVN), Vietnam National Oil and Gas Group (PVN), relevant agencies and proposed to pilot PVN's offshore wind power project.

At the same time, review and complete legal documents, create conditions for domestic and foreign investors to participate, and be determined to build an offshore wind power industry, making Vietnam a regional offshore wind power center.

Regarding the two LNG Nhon Trach 3 and 4 thermal power plant projects, the handover, land lease and infrastructure construction work have been basically completed. However, the compensation and site clearance work for the power grid projects to release capacity for the LNG Nhon Trach 3 and 4 thermal power plants is very slow. In the coming time, EVN and PVN need to soon negotiate and agree to sign a power purchase agreement (PPA).

Dong Nai province leaders said the locality is urgently carrying out procedures to locally adjust the General Planning of Nhon Trach New Urban Area.

The Deputy Prime Minister requested Dong Nai province to focus on directing and closely coordinating with the Ministry of Natural Resources and Environment to complete the handover of land for power grid projects to release capacity for Nhon Trach 3 and 4 LNG thermal power plants by the end of 2024.

Tích cực gỡ khó, thúc đẩy tiến độ các công trình, dự án năng lượng trọng điểm- Ảnh 5.

Delegates discussed the mechanism for developing electricity, first of all to remove the remaining difficulties and obstacles of the two LNG Nhon Trach 3 and 4 thermal power plant projects; the Lot B Gas - Power Project Chain; the Quang Trach Power Center... - Photo: VGP/Minh Khoi

Regarding projects in the Quang Trach Power Center, the Quang Trach 1 Thermal Power Plant project has reached 63% but is still facing difficulties in site clearance for some items. The Quang Trach 2 Thermal Power Plant project is adjusting its investment policy to switch to using LNG.

The Steering Committee discussed the mechanism for gas-fired power development, first of all to remove the remaining difficulties and obstacles of the two LNG Nhon Trach 3 and 4 thermal power plant projects; Lot B Gas - Power Project Chain; Quang Trach Power Center...; solutions to handle slow-progressing and slow-implementing power source projects; directions to completely resolve a number of renewable energy power projects that violate legal regulations during the investment and construction process so that they can be put into operation to limit waste of resources and increase power source capacity for the power system.

Concluding the meeting, Deputy Prime Minister Tran Hong Ha highly appreciated the commitment of localities to complete site clearance and hand over to investors to carry out items and works related to Nhon Trach 3 and 4 thermal power projects and the power grid to release capacity, and "need to closely monitor the progress of implementation".

Tích cực gỡ khó, thúc đẩy tiến độ các công trình, dự án năng lượng trọng điểm- Ảnh 6.
The Deputy Prime Minister assigned the Ministry of Industry and Trade, the Ministry of Planning and Investment, the Ministry of Justice and localities to review and specifically report the number of power source projects that are behind schedule... - Photo: VGP/Minh Khoi

The Deputy Prime Minister requested the Ministry of Industry and Trade and localities to coordinate with the Ministry of Public Security and relevant agencies to review solar power projects mentioned in the conclusion of the Government Inspectorate and transfer them to the investigation agency.

Classify projects that show no signs of criminal violations or errors, can be remedied according to inspection and examination conclusions... and meet the criteria of system safety, transmission technology, and economic efficiency to put into operation.

For gas-fired thermal power projects facing difficulties in the mechanism for determining the contracted electricity output (QC), electricity purchase price, etc., the Deputy Prime Minister requested corporations and enterprises to proactively participate with the Ministry of Industry and Trade to complete the amendment and promulgation of relevant circulars; prepare documents to report to the Government to submit to the National Assembly to issue a Resolution on mechanisms and policies for gas-fired power projects.

Regarding the offshore wind power development pilot project, the Deputy Prime Minister requested that there must be a specific project and model (exporting the entire project, producing green fuels (hydrogen, ammonia), transmitting to the national grid), and implementation methods (domestic enterprises, joint ventures with foreign countries) to determine the "problems" that need to be solved regarding the legal corridor, investigation, survey, planning... "so that the Prime Minister can approve it and implement it synchronously and comprehensively".

The Deputy Prime Minister assigned the Ministry of Industry and Trade, the Ministry of Planning and Investment, the Ministry of Justice and localities to review and specifically report the number of power source projects that are behind schedule, clarify "which projects can be handled, which projects cannot be handled", and recommend competent authorities to handle them according to the provisions of law.

The Ministry of Industry and Trade urgently researches and develops a project to proactively compensate for capacity for power source projects that are behind schedule compared to the Plan for implementing the 8th Power Plan with solutions and mechanisms to decide on investment in new power source projects, mobilizing other power sources: Hydropower, solar power, rooftop solar power, solar power storage systems, etc.



Source: https://baotainguyenmoitruong.vn/tich-cuc-go-kho-thuc-day-tien-do-cac-cong-trinh-du-an-nang-luong-trong-diem-378737.html

Comment (0)

No data
No data

Same tag

Same category

Same author

Figure

French father brings daughter back to Vietnam to find mother: Unbelievable DNA results after 1 day
Can Tho in my eyes
17-second video of Mang Den so beautiful that netizens suspect it was edited
The primetime beauty caused a stir because of her role as a 10th grade girl who is too pretty even though she is only 1m53 tall.

No videos available