On January 30, Politburo member, Secretary of the City Party Committee, Head of the Steering Committee for the implementation of the Ring Road 4 construction investment project - Hanoi Capital Region Dinh Tien Dung visited, wished a happy New Year and gave gifts to encourage workers and laborers working on the Ring Road 4 construction site in Hanoi, Bac Ninh and Hung Yen.
Mr. Dinh Tien Dung and the delegation visited, wished a happy New Year, and gave gifts to workers and laborers who are constructing Ring Road 4 at four locations: the intersection between Ring Road 4 and District Road 12 (Km74+250), Dinh Du Commune, Van Lam District, Hung Yen Province; the intersection between Ring Road 4 and National Highway 38 (Km88+100) in Hoang Xa Village, Ninh Xa Commune, Thuan Thanh Town, Bac Ninh Province; Office of the Executive Board of Bidding Package No. 08/TP2-XL (Km7+900 of Ring Road 4), the intersection between Ring Road 4 and Me Linh Axis Road, Chu Phan Commune, Me Linh District, Hanoi; Office of the Executive Board of Bidding Package No. 09/TP2-XL (Km12+900 of Thang Long Highway intersecting with Ring Road 4 at Km28+900).
Secretary of the Hanoi Party Committee Dinh Tien Dung and Secretary of the Hung Yen Provincial Party Committee Nguyen Huu Nghia presented gifts to workers on duty at the construction site of Ring Road 4 - Hanoi Capital Region in Dinh Du commune, Van Lam district (Hung Yen province).
Wishing a Happy New Year to cadres, workers, and laborers at the construction site, Mr. Dinh Tien Dung stated that Ring Road 4 is a national key project, large-scale, and requires fast construction progress.
The project has an important meaning in connecting regions, unlocking resources, creating development momentum not only for Hanoi, but also for the Capital Region, the Northern Key Economic Zone, and the Red River Delta. The project has a broad and long-term significance, so participating in the construction of the route is truly an honor and pride for every cadre, employee, and worker.
Mr. Dung also acknowledged and praised the construction results of the contractors, officers, employees and workers who have created a very positive and joyful shape for the road.
Secretary of the Hanoi Party Committee Dinh Tien Dung visited, wished a happy new year and presented gifts to workers on duty at the construction site of Ring Road 4 - Hanoi Capital Region in Dinh Du commune, Van Lam district (Hung Yen province).
However, affirming that difficulties still lie ahead, the Head of the Project Steering Committee requested that units and each officer, employee, and laborer who has tried, need to try harder, seize opportunities, make the most of time, work through Tet to speed up progress, and ensure project quality.
Mr. Dung also noted that agencies and units should pay attention to taking care of the regime, paying salaries and bonuses promptly so that employees can work with peace of mind and contribute.
Secretary of the Hanoi Party Committee Dinh Tien Dung visited, wished a happy new year and presented gifts to workers on duty at the construction site of Ring Road 4 - Hanoi Capital Region in Thuan Thanh commune (Bac Ninh province).
On the occasion of welcoming the Year of the Dragon, Secretary of the City Party Committee Dinh Tien Dung wished all employees and workers of the construction units of Ring Road 4 a new year of good health, happiness and determination to successfully carry out the noble and very proud task: Building Ring Road 4 to ensure quality and progress.
Visiting and wishing a Happy New Year to officers and soldiers of Corps 12 (Truong Son Construction Corporation) at the construction site of Ring Road 4 - Hanoi Capital Region in Me Linh district.
According to the Hanoi City Traffic Project Management Board, up to now, Hanoi City and the two provinces of Bac Ninh and Hung Yen have approved plans and reclaimed 1,312.05/1,390.49 hectares of land, reaching 94.36%; moved 14,930/16,417 graves, reaching 90.94%.
Of which, Hanoi reclaimed 768.99/791.21 hectares of land, equivalent to 97.19%; relocated 9,874/10,232 graves, reaching 96.5%. Hanoi has also built 13 resettlement areas, with a total area of 32.5 hectares, of which 5/13 areas have been basically completed and 8/13 areas are under construction, of which, Soc Son and Thuong Tin districts have organized a lottery for 140 households eligible for resettlement.
Visiting, wishing a happy new year, and giving gifts to workers on duty at the construction site of Ring Road 4 - Hanoi Capital Region in Me Linh district.
Hung Yen province recovered 195.6/230.2 hectares of land, reaching 85%; moved 3,587/4,239 graves, reaching 84.6%. Bac Ninh province recovered 347.46/369.08 hectares of land, reaching 94.14%; moved 1,469/1,946 graves, reaching 75%.
In addition, the exploitation of materials under a special mechanism has been initially resolved, basically meeting the material demand according to the construction progress of the Project (2 sand mines Chu Phan, Thach Da 1; 1 Go Dinh soil mine have been confirmed by the Hanoi People's Committee for contractors to register for exploitation. Of which, Chu Phan sand mine has started exploiting about 0.15 million cubic meters).
Secretary of Hanoi Party Committee Dinh Tien Dung speaks.
Secretary of the Hanoi Party Committee Dinh Tien Dung visited and wished a Happy New Year to workers and laborers working at the construction site of Ring Road 4 - Hanoi Capital Region in Hoai Duc district.
Along the entire parallel route in Hanoi, contractors have organized 32 construction teams, including 23 road construction teams and 9 bridge construction teams. The total contract value of the 4 packages under Component Project 2.1 is about 4,691 billion VND; the construction output to date is estimated at about 586 billion VND (equivalent to 12.5% of the contract value).
In Hung Yen province, 4 road construction projects have been deployed, with construction output reaching 25 billion VND, equal to 2% of the total contract value of the package.
In Bac Ninh province, the parallel road is divided into 3 segments corresponding to 3 construction packages. To date, only one segment has been constructed with a construction output of 15 billion VND, equivalent to 1.7% of the total contract value .