Chairman of the Hanoi People's Committee Tran Sy Thanh has just urged relevant units to start the expressway project on Ring Road 4 in May and complete the project's urban roads in October 2025.
The Office of the Hanoi People's Committee has just issued a notice of the conclusion and direction of the Chairman of the Hanoi People's Committee, Tran Sy Thanh, at the meeting to listen to reports on the progress and implementation of the Ring Road 4 - Capital Region Investment and Construction Project.
Accordingly, after listening to the report of the City Traffic Construction Investment Project Management Board, Mr. Tran Sy Thanh requested the districts to completely resolve the remaining land area to be recovered, completed before April 15, 2025. According to Mr. Thanh, this is the final deadline, no later than that.
The Chairman of the Hanoi People's Committee assigned Me Linh district to continue focusing on site clearance work in the area to ensure completion according to the above schedule.
In case households have petitions that are contrary to regulations, violate land clearance policies, intentionally cause complications or oppose, and affect the progress of investment projects, consider applying administrative enforcement measures to recover land to ensure progress.
The Chairman of the Hanoi People's Committee assigned two Vice Chairmen, Mr. Duong Duc Tuan and Mr. Nguyen Trong Dong, to continue directing and thoroughly resolving difficulties and problems in Me Linh area.
For Component Project 2.1, the Chairman of the Hanoi People's Committee assigned the City Traffic Construction Investment Project Management Board to urge contractors to complete the project in October 2025, welcoming the City Party Congress.
The parallel road (urban road) is component project 2.1 of the Ring Road 4 project - Capital region. The parallel road section through Hanoi is over 57 km long, passing through the districts: Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai, Thuong Tin.
For component project 3 (expressway construction investment), the City Traffic Construction Investment Project Management Board urgently prepares relevant documents so that after selecting an investor, it can immediately handle necessary procedures, ensuring the construction progress on May 19, 2025.
The Ring Road 4 - Capital Region project started construction in June 2023. The total length of the route is 112.8km, of which the section passing through Hanoi is 56.5km, Hung Yen is 20.3km, Bac Ninh is 21.2km. The total investment of the project is about 85,813 billion VND.
Regarding progress and construction start time, relevant units expect to complete Ring Road 4 - Capital region in 2026 and put it into operation in 2027.
Research on new technological solutions for construction of Ring Road 4
41,000 billion VND compensation for site clearance of Ho Chi Minh City Ring Road 4
Prime Minister asks Bac Ninh to speed up progress of Ring Road 4 project
Source: https://vietnamnet.vn/chu-tich-ha-noi-chot-thoi-diem-hoan-thanh-duong-vanh-dai-4-2382152.html
Comment (0)