The Ministry of Construction directed investors and contractors to complete all related procedures to hand over and put into operation the last 70km of the Van Phong - Nha Trang expressway on the occasion of April 30.
This is one of the instructions of Deputy Prime Minister Le Thanh Long, Head of Inspection Team No. 3, in the conclusion of the working session on reviewing and removing difficulties and obstacles of four projects: Chi Thanh - Van Phong and Van Phong - Nha Trang under the North - South Eastern Expressway Construction Project in the 2021-2025 period, component project 1 and component project 3 under the Khanh Hoa - Buon Ma Thuot Expressway Construction Investment Project.
Deputy Prime Minister Le Thanh Long inspects the progress of the Khanh Hoa - Buon Ma Thuot expressway project (Photo: Tuong Cao Son).
In conclusion, the Deputy Prime Minister emphasized the four projects of the Chi Thanh - Van Phong and Van Phong - Nha Trang sections of the North - South Eastern Expressway, component project 1 and component project 3 of the Khanh Hoa - Buon Ma Thuot Expressway with a total length of about 199.3km, accounting for about 20% of the total km of expressway to be completed in 2025. Therefore, the completion of these four projects is extremely important.
Deputy Prime Minister Le Thanh Long requested the Ministry of Construction, relevant ministries, agencies, local People's Committees, investors, contractors, supervision consultants, relevant organizations and individuals to urgently and seriously implement the tasks and solutions set out to complete the four projects on schedule, ensuring quality, safety, efficiency and compliance with regulations.
In particular, the People's Committees of Khanh Hoa and Dak Lak provinces continue to be determined and resolute in propagating and mobilizing people to promptly hand over the site and direct the acceleration of the relocation of technical infrastructure works, completing and handing over the entire site before March 31.
Ministry of Construction, Khanh Hoa Provincial People's Committee, Dak Lak Provincial People's Committee (as the governing body) direct investors, consultants, and contractors to update the overall construction progress and detailed construction progress.
It clearly defines the "critical" path to complete projects in 2025 (there must be solutions to compensate for the delayed volume, and reserve time in case of unfavorable weather conditions).
Increase human resources, construction equipment, and financial resources to organize "3 shifts, 4 crews" construction to ensure completion of projects according to plan.
At the same time, direct to speed up the implementation of the remaining items of the intelligent traffic management system, toll stations, vehicle load control works, and rest stops to complete synchronously when putting the works into operation.
The Ministry of Construction, as the standing agency of Inspection Team No. 3, continues to proactively monitor and grasp the progress of project construction, coordinate with the Government Office to urge competent agencies to perform tasks, promptly synthesize and report to competent authorities to resolve difficulties and problems.
Deputy Prime Minister Le Thanh Long also assigned specific tasks to each project.
Specifically, for the Chi Thanh - Van Phong project, the Ministry of Construction directed the investor and contractor to organize construction to ensure completion of the project in 2025, paying attention to strengthening construction teams and proactively sourcing materials to build the roadbed.
Actively coordinate materials between bid packages to ensure sufficient source of filling materials to complete the roadbed loading work in March 2025 (calculate necessary technical solutions to shorten settlement waiting time).
For sections that do not require weak ground treatment, focus on accelerating construction progress to complete in September 2025.
For the Van Phong - Nha Trang project, the Ministry of Construction directed the investor and contractor to complete all related procedures to hand over and put into operation the last 70km of the route on the occasion of April 30.
Taking advantage of favorable weather conditions, construction was organized in "3 shifts, 4 teams" to complete the entire 13km first section of the route, ensuring the goal of completing the entire route by June 30, 2025.
Regarding the component project 1 of the Khanh Hoa - Buon Ma Thuot expressway, the Deputy Prime Minister assigned the People's Committee of Khanh Hoa province to focus on leadership, direct resolutely, and resolve problems to hand over the remaining 2.2km of land due to 40 households, while proactively and proactively preparing for enforcement options.
Speed up the relocation of 3 220KV power line locations. Complete the handover of the entire site in March 2025 in accordance with the Prime Minister's direction.
The investor and contractor updated the progress and organized construction in "3 shifts, 4 teams" to complete the roadbed, foundation, traffic safety items, etc. to ensure the goal of completing the first 20km of the route in 2025 as planned.
As for the component project 3 of the Khanh Hoa - Buon Ma Thuot expressway, the Dak Lak People's Committee was assigned to urgently complete the site clearance procedures for the additional 10 hectares and speed up the relocation of the 500 kV power line; and direct the Department of Agriculture and Environment to handle the procedures for the contractor to lease land at the Ea Kenh mine.
Guide investors, contractors, and District People's Committees on procedures for handing over project surplus material storage sites for management according to regulations. Progress to be completed in March 2025.
Source: https://www.baogiaothong.vn/khai-thac-70-km-cao-toc-van-phong-nha-trang-dip-30-4-192250318174713367.htm