Since the beginning of the year, Van Don district has actively promoted the disbursement of public investment capital, with high determination and great efforts, striving to complete 100% of the year's assigned plan.
According to the report of the District Construction Investment Project Management Board, the total public investment capital in 2024 of Van Don is arranged at over 630 billion VND, allocated to 17 transitional projects and 15 newly started projects. Currently, a number of projects invested from the district's public investment capital have been completed and put into operation, showing clear effectiveness, becoming an important highlight in the development of many areas of the locality.

Identified as key projects with large disbursement capital in Van Don in the year, Ha Long I Primary School is invested in a high-quality model, with 4 blocks of 3 floors, with a total of more than 20 classrooms and auxiliary works, with a total investment of over 110 billion VND; Van Don Economic Zone Cultural - Sports Center has an investment scale of a 1,300-seat gymnasium, outdoor swimming pool area, football field, auxiliary works, with a total investment of over 90 billion VND.
In 2024, the public investment capital allocated for these two projects is 73 billion VND (Ha Long I Primary School is 44 billion VND, Cultural - Sports Center is 29 billion VND). Up to now, both projects have been completed and payment and settlement are being carried out according to regulations. Along with the above 2 projects, the transitional projects using public investment capital of Van Don are also being urgently promoted according to plan and completing payment and settlement procedures according to regulations.
Deputy Director of the Van Don District Construction Investment Project Management Board, Tran Quoc Hoan, said: We always closely connect with contractors and construction units to find solutions to overcome difficulties to complete the project as soon as possible. Accordingly, the District Construction Investment Project Management Board has directed contractors to construct transitional projects to concentrate machinery, equipment, supplies, materials, and overcome all difficulties in weather and labor to speed up the construction progress. At the same time, it requires supervisory units to regularly be present at the site to check the quality and volume and coordinate with contractors to make statistics on the volume to disburse capital, to avoid errors or projects that do not meet technical requirements.

However, to complete the disbursement of public investment capital, Van Don still has a lot of work to do. Currently, the district is urgently and resolutely completing investment procedures (especially projects implemented in 2024) to ensure compliance with regulations and procedures to promptly implement projects and proactively coordinate with relevant departments, branches and units to promptly handle procedures according to regulations. Further strengthen the inspection and supervision of construction quality of basic construction projects, resolutely not allowing violations of investment procedures and poor quality of works.
In addition, regularly urge and inspect the implementation of key projects in 2023, start new projects in 2024, strive to exceed construction progress, ensure project quality, and ensure the disbursement of all planned capital sources in 2024 before December 31, 2024. Focus on directing drastic solutions to site clearance work, not to delay construction progress. Assign and assign specific responsibilities to units and localities for site clearance work of projects.
Source
Comment (0)