TPO - Bac Ninh province is urgently constructing the approach road to Ha Bac 2 bridge connecting Bac Giang and Bac Ninh provinces to soon put the project into use.
TPO - Bac Ninh province is urgently constructing the approach road to Ha Bac 2 bridge connecting Bac Giang and Bac Ninh provinces to soon put the project into use.
Previously, Tien Phong newspaper reported that Bac Giang province had completed the construction of the approach road and Ha Bac 2 bridge (total investment of more than 350 billion VND) across Cau river connecting Bac Giang province with Bac Ninh province, waiting for the completion of the approach road on Bac Ninh province's side to put the bridge into use. |
According to Tien Phong newspaper reporters at the construction site on November 8, the Bac Ninh Province Urban Development Area Management Board - the project investor on the Bac Ninh side and the contractor mobilized dozens of workers and about 30 vehicles and machinery to construct the access road to Ha Bac 2 bridge. Photo: Nguyen Thang |
The connection point with Ha Bac 2 bridge on the Bac Ninh side is being urgently constructed. Photo: Nguyen Thang |
According to the leader of the Bac Ninh Province Urban Development Management Board, the DT.277B project is 4.9km long (including the road leading to Ha Bac 2 Bridge). Photo: Nguyen Thang |
The starting point of the route connects with DT.285B in Thuy Hoa commune, Yen Phong district; the end point of the route connects with the Ha Bac 2 Bridge approach road in Dung Liet commune, Yen Phong district. Photo: Nguyen Thang |
In July, the site clearance unit (Yen Phong District Construction Project Management Board) handed over 2.6km of site to the investor; in August, an additional 1.25km was handed over. Photo: Nguyen Thang |
The contractor is working in 3 shifts to complete the project soon. Photo: Nguyen Thang |
For the section handed over in July (2.6km), the contractor plans to complete the C16 asphalt paving in December. For the section handed over in August (1.25km), the contractor plans to complete the crushed stone foundation and C19 asphalt paving in January 2025. |
Currently, the investor is actively coordinating with the site clearance unit and the People's Committee of Yen Phong district to focus on removing difficulties and obstacles, striving to complete site clearance for the remaining locations in December. Photo: Nguyen Thang |
The investor will hand over the site to the contractor immediately after the district-level site clearance council pays compensation and supports people whose land is recovered for construction, striving to complete the entire project and open the route according to the signed contract schedule in March 2025, putting Ha Bac 2 bridge into use, contributing to the economic and social development of Bac Ninh and Bac Giang provinces. |
Source: https://tienphong.vn/gap-rut-xay-duong-dan-len-cau-hon-350-ty-roi-bo-khong-post1689957.tpo