Bringing the 500KV line 3 project to the finish line on June 30

Việt NamViệt Nam01/06/2024

Vietnam Electricity Group has mobilized 1,500 skilled engineers and workers to support this key project.

To shorten the construction time and bring the 500KV line 3 project to the finish line as committed on June 30, Vietnam Electricity Group has mobilized 1,500 engineers and skilled workers from 5 power corporations to support this key project.

Tập đoàn Điện lực Việt Nam đã huy động 1.500 kỹ sư, công nhân có tay nghề để tiếp sức cho dự án trọng điểm này.
Vietnam Electricity Group has mobilized 1,500 skilled engineers and workers to support this key project.

With a length of 519 km, the 500kV line 3 project includes 1,177 pole foundation positions, and up to now, the entire project has completed nearly 61% of the erection. According to the assignment of tasks, the mobilized human resources are divided into 119 teams, each team has about 15 people. For the electricity workers, these days, putting aside family matters and focusing on contributing to the project's progress is a great honor.

Mr. Nguyen Hoang Thang - Technical Team Staff, Ho Chi Minh City High Voltage Grid Company said: "Right when the mobilization of the City Electricity Company started, I just thought that I was eating the electricity company's rice, so when the electricity company needed me, I volunteered."

Mr. Tran Cong Dep - Team Leader of Team 9, Shock Team supporting 500KV line 3 shared: "To prepare well for this job, there are many tasks. First is to choose brothers with good health and enough experience. Up to this moment, it can be said that the team leadership has grasped the construction design drawings and has also studied very carefully to prepare the most necessary construction tools".

Shorten construction time, bring the 500KV line 3 project to the finish line as committed on June 30.

There are only 30 days left to complete the project, so increasing manpower will ensure shortening the construction time.

Mr. Nguyen Duy Thanh - Worker of Quang Ngai Electricity Company commented: "With a distance of more than 700 km, we came here determined to integrate into the common life of the people here, to adapt and perform well the task, completing on schedule the 500KV line 3 project".

Mr. Nguyen Ngoc Khanh - Director of Ho Chi Minh City High Voltage Grid Company shared: "Not only did we choose the frontline team to consider everything else, but there was also a team to take care of logistics for the brothers, including accommodation and rest conditions. In particular, these were the means to ensure safety and to do their jobs well."

With the motto of pulling wires as soon as the poles are erected, the 500kV line 3 project, once completed, will increase the transmission capacity between the Central and Northern regions from the current 2,200 MW to about 5,000 MW and increase the amount of commercial electricity by over 20 billion kWh, meeting the electricity demand for economic development.

The 500KV line 3 project from Quang Trach, Quang Binh to Pho Noi, Hung Yen, with a length of about 519 km, includes 1,177 pole foundation locations. Up to now, 100% of the locations have been handed over to contractors by the 9 localities where the project passes through.

Localities: Thai Binh, Thanh Hoa, Nghe An said that the project construction site has been completed and handed over to the investor. Particularly in Thai Binh province, with the drastic participation of local authorities, the clearance work was carried out the earliest. With a length of about 39 km passing through the province, 107 column foundation locations and anchoring spaces have been handed over to construction units to implement the project. Along with that, local human resources are also proactive, ready to support when necessary, ensuring good security and order at project implementation locations.

vtv.vn

Source

Comment (0)

No data
No data

Same tag

Same category

Young people "revive" historical images
Close-up of the soldiers' hard training hours before the April 30th celebration
Ho Chi Minh City: Coffee shops decorated with flags and flowers to celebrate the 30/4 holiday
36 military and police units practice for April 30th parade

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product