Vietnam.vn - Nền tảng quảng bá Việt Nam

Ensuring rights for people affected by National Highway 14E project

Việt NamViệt Nam12/02/2025


7.jpg
Vice Chairman of the Provincial People's Committee Tran Nam Hung listened to Thang Binh district report on land acquisition and clearance problems. Photo: CONG TU

Reporting to the leaders of Quang Nam province, Mr. Que Hai Trung - Deputy Director of Project Management Board 4 (project management unit) said that up to now, Hiep Duc district has handed over 26.83/30.2km (accounting for 88.84%) of the length of the site. At the handed-over location, there is a 1.2km long section that cannot be accessed for construction; 50 sections/15.93km have longitudinal ditches and widening but are not yet qualified for asphalt concrete paving (each section's length is under 500m).

There are many reasons for the land acquisition and clearance problems in Hiep Duc. For example, there is no land price framework for the Vuon Che resettlement area to have a basis for planning the relocation of resettled households in Binh Lam commune; there are no results of handling 8 households outside the land acquisition and clearance line; the difference in support prices for garden and pond land between the new and old Land Law guidelines makes many households disagree; 4 medium voltage power stations have not been relocated.

In addition, the compensation and support plans of many households have not been approved yet; some households have received money but have not started construction.

Project Management Board 4 recommends that the Provincial People's Committee prioritize the settlement of procedures on the Tea Garden land price frame; compensation and support plans for households outside the GPMB line according to the submission of the Hiep Duc District People's Committee.

Prioritize early settlement and handover of the site in Binh Lam commune related to 3 households of Ly Mien, Le Thi Toi and Nguyen Thi Ta so that the contractor can access 1.2km of the site that has been handed over on the Viet An bypass. The district mobilizes households to approve the plan to receive money and hand over the site.

[VIDEO] - The working group inspected land acquisition and clearance at the railway intersection through Thang Binh district:

Up to now, Thang Binh district has handed over 14.86/17.4km (85.4%); of which, 9.19km/74 sections have been handed over but only the longitudinal ditches and widening have been constructed. Many sections have been handed over in a "leopard skin" style, so the construction cannot be completed in a rolling manner. For the railway overpass, the district has approved the plan for 45 households, but only 39 households have received the money, 6 households have not agreed to receive the money, and 14 households have not approved the plan.

The project management unit recommends that Thang Binh district soon complete procedures to approve the plans, especially the scope of the railway overpass. In addition, priority should be given to land acquisition and site clearance to connect 3 longitudinal ditches to the discharge gate to avoid local flooding and damage to the road surface in Binh Quy commune; and to connect to construct crushed stone and asphalt concrete foundations in some sections through Binh Quy, Binh Dinh, Binh Tri, and Binh Lanh communes.

2(1).jpg
Comrade Tran Nam Hung looked at the documents provided by Mr. Dang Ha's household (Binh Quy commune, Thang Binh). Photo: CONG TU

Meeting with some households affected by land acquisition for the construction of the railway overpass, Vice Chairman of the Provincial People's Committee Tran Nam Hung explained and analyzed in detail the legal issues that people did not understand.

The provincial leaders also affirmed that they always thoroughly grasp the localities' efforts to maximize the benefits for the people, based on the provisions of the law. Therefore, they hope that the people will pay attention and support the general policy, agree to hand over the site for the contractor to construct the project for the common benefit of the province and the whole society.

Project Management Board 4 said that the project through Phuoc Son district (from km62+926 - km89+700) currently only has to clear land for 2 households in Phuoc Hoa commune with a length of 240m; stuck with the Viettel broadcasting station anchor at km77+00. The unit proposed that the district speed up compensation procedures to hand over all of this remaining land.



Source: https://baoquangnam.vn/dam-bao-quyen-loi-cho-nguoi-dan-bi-anh-huong-du-an-quoc-lo-14e-3148871.html

Comment (0)

No data
No data

Same tag

Same category

Spectacular start of Vietnamese film market in 2025
Phan Dinh Tung releases new song before concert 'Anh trai vu ngan cong gai'
Hue National Tourism Year - 2025 with the theme "Hue - Ancient Capital - New Opportunities"
Army determined to practice parade 'most evenly, best, most beautiful'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product